Agenda and minutes

Planning Committee - Wednesday 7 August 2013 6.00 pm

Venue: Council Chamber. View directions

Contact: Lyndsey Parnell  Members' Services Officer

Items
No. Item

29.

Apologies for Absence.

Minutes:

Apologies for absence were received from Councillors Pauline Allan, Roy Allan and Chris Barnfather.

30.

To approve, as a correct record, the minutes of the meeting held on 17 July 2013. pdf icon PDF 54 KB

Minutes:

RESOLVED:

 

That the minutes of the above meeting, having been circulated, be approved as a correct record, subject to the following amendments:

 

      i.        That Councillor Lawrence be recorded as present.

     ii.        That the word “retrospective” be removed from minute number 20, so that it reads:

 

“RESOLVED to GRANT PLANNING PERMISSON subject to the following conditions”

 

    iii.        That the following be added to minute number 16:

 

“At the request of Members, the Chair agreed to meet with the Service Manager, Planning and Economic Development to agree a procedure for reporting the outcome of decisions delegated by the committee to the Committee.

31.

Declaration of Interests

Minutes:

All Councillors declared a non-pecuniary interest in Application 2013/0560 as Members of Gedling Borough Council.

32.

Application No. 2010/0936 - 2 & 2A Sandford Road, Mapperley, Nottinghamshire. pdf icon PDF 1 MB

Minutes:

 

To GRANT PLANNING PERMISSION subject to the applicant entering into a Section 106 Agreement with the County Council for a contribution towards Education and subject to the following conditions:

 

Conditions

 

1.         The development must be begun not later than three years beginning with the date of this permission.

 

2.         The development hereby approved, other than the means of enclosure of the site and the details of new tree planting adjacent to the boundary with Porchester Road shown on the submitted plans, shall be built in accordance with drawing nos.0001 Rev A, 0011 Rev A and 0006 Rev A received on 15th April 2013, drawing nos.0100 Rev A, 2000 Rev A, 0004 Rev C, 0005 Rev B, 0008 Rev B, 0009 Rev C received on 11th June 2013, drawing no. 0010 Rev C received on 20th June 2013 and drawing no.0003 Rev D received on 18th July 2013.

 

3.         Before development is commenced a sample of the materials to be used in the external elevations of the building, including to the exterior wall of the proposed vehicular access ramp, shall be submitted to and approved in writing by the Borough Council.

 

4.         Before development is commenced precise details of the materials to be used in surfacing of external areas outside of the building including anti-skid surfacing to the proposed ramp shall be submitted to and approved in writing by the Borough Council.

 

5.         The development shall be completed in the external elevation materials and the surfacing materials approved under Conditions 3 and 4 of this consent.

 

6.         The development hereby permitted shall not commence until drainage plans for the disposal of surface water (including to the proposed car park and vehicular access ramp) and the disposal of foul sewage from the site and buildings/structures have been submitted to and approved by the Borough Council.

 

7.         The development shall be completed in accordance with the drainage plans approved under condition 6 of this consent.

 

8.         Before development commences a method statement setting out measures to ensure the safe removal of the trees to the boundary with Porchester Road shall be submitted to and approved in writing by the Borough Council.

 

9.         The trees to the boundary with Porchester Road shall be removed in accordance with the method statement approved under condition 8 of this consent.

 

10.       Before development is commenced, notwithstanding the details of enclosure shown on the approved plans, there shall be submitted to and approved by the Borough Council precise details of the means of enclosure to the site including any works to the hedge to the boundary with no.7 Hilton Road.

 

11.       The means of enclosure shall be erected in accordance with the details approved under condition 10 of this consent and retained at all times unless alternative means of enclosure are agreed in writing with the Borough Council.

 

12.       Before development is commenced there shall be submitted to and approved by the Borough Council a landscape plan of the site showing precise details of retaining structures adjacent to  ...  view the full minutes text for item 32.

33.

Application No. 2012/1335 - Former Gedling Colliery, Arnold Lane, Nottinghamshire. pdf icon PDF 3 MB

Minutes:

That the Borough Council supports the GRANT OF PLANNING PERMISSION, subject to the applicant entering into a Section 106 Agreement with the Borough Council for a financial contribution towards off-site biodiversity mitigation and compensation works and subject to the following amended conditions:

 

Conditions

 

1.         The development must be begun not later than three years beginning with the date of this permission.

 

2.         The development hereby permitted shall be constructed in accordance with the following approved plans and documents: Juwi Rack (4020 1069-69.2), Technical Details 2 (4020 1069-69.2), Technical Details - Substation 2 (4020 1069-69.2), Technical Details 4 - Station (4020 1069-69.2) and Technical Details - Substation (4020 1069-69.2), deposited on 21st November 2012; Site Location Plan (RG-M-02 Rev E), Overall Module Layout (4020 1069-10.00) and Spring Lane Proposed Junction Layout (0435-GA-01D Rev D), received on 7th June 2013; Technical Details 1 (4020 1069-69.2), received on 23rd July 2013; and the Extended Phase I Habitat Survey, including Desk Study, (SLR Ref: 424-04114-00003), June 2013 Rev 01, received on 28th June 2013.

 

3.         Before development is commenced there shall be submitted to and approved in writing by the Borough Council detailed construction and engineering drawings showing any proposed changes to existing levels and contours across the site in excess of 1 metre.  The development shall be constructed in accordance with the approved drawings and the finished levels and contours shall be retained without further alteration for the lifetime of the development.

 

4.         Before development is commenced there shall be submitted to and approved in writing by the Borough Council details of the materials to be used in the construction of the proposed temporary construction access and HGV turning area.  The temporary construction access and HGV turning area shall be provided in accordance with the approved details prior to work commencing on the installation of the solar arrays, sub-stations, cable trenches or fencing and shall be retained until the development hereby approved is first brought into use.

 

5.         Before development is commenced there shall be submitted to and approved in writing by the Borough Council, details of a surface water drainage scheme for the site, based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the development.  The scheme shall subsequently be implemented in accordance with the approved details before the development is completed and shall be retained for the lifetime of the development, unless otherwise prior agreed in writing by the Borough Council.  The scheme to be submitted shall demonstrate the utilisation of holding sustainable drainage techniques; the limitation of surface water run-off to equivalent greenfield rates; the ability to accommodate surface water run-off on-site up to the critical 1 in 100 year event plus an appropriate allowance for climate change, based upon the submission of drainage calculations; and responsibility for the future maintenance of drainage features.

 

6.         Unless otherwise agreed by the Borough Council, development must not commence until the following has been complied with: (a) Site Characterisation- An assessment of the nature and extent of  ...  view the full minutes text for item 33.

34.

Application No. 2013/0560 - Site of the Druid's Tavern, High Street, Arnold. pdf icon PDF 4 MB

Minutes:

To GRANT PLANNING PERMISSION subject to the following conditions:

 

Conditions

 

1.         The development must be begun not later than three years beginning with the date of this permission.

 

2.         The development hereby approved shall be carried out in accordance with the approved plans (drg. nos.G11/CP1/HSA03A and G13/CP1/HSA06A) deposited on the 23rd May 2013, revised plans (drg nos. G13/CP1/HSA09A, G13/CP1/HSA11A)  and landscaping plans in relation to planting areas 1, 2,3 and 4 deposited on the 25th June 2013.

 

3.         The proposed lighting and CCTV hereby approved shall be implemented and maintained in accordance with the details indicated on drg. nos. G13/CP1/HSA03A and G13/CP1/HSA06A and specifications deposited on the 23rd May 2013 unless otherwise agreed in writing by the Borough Council.

 

4.         The landscaping scheme hereby approved shall be carried out in accordance with the details of planting areas 1-4 and drg. no. G13/CP1/HSA11A deposited on the 25th June 2013 in the first planting season following the substantial completion of the development and any planting material which becomes diseased or dies within five years of the completion of the development shall be replaced in the next planting season by the applicants or their successors in title.

 

5.         No part of the development hereby permitted shall be brought into use until the boundary wall hereby approved is erected in accordance with details indicated on the revised plan drg. no. G11/CP1/HSA03A deposited on the 23rd May 2013, thereafter the boundary wall shall be retained in accordance with the approved details for the lifetime of the development.

 

6.         No development shall commence on any part of the application site until such time details of construction and surfacing materials to be used has been submitted to and approved in writing by the Borough Council. Works shall be completed in accordance with the approved details.

 

7.         No part of the development hereby permitted shall be brought into use until access/exit arrangements including modification to the existing one (as shown on plan reference G11/CP1/HSA03A deposited on the 27th November 2012) are available for use and constructed in accordance with the Highway Authority specifications to the satisfaction of the Borough Council. The access/exit arrangements shall be maintained as such for the lifetime of the development.

 

8.         No part of the development hereby permitted shall be brought into use until the access ways within the car parking layout, parking and turning areas as shown on the approved plans are surfaced in a hard bound material (not loose gravel). The access ways, parking and turning areas shall then be maintained in such hard bound material for the life of the development.

 

9.         Prior to the development hereby approved first being brought into use, individual parking spaces shall be clearly marked out on site in accordance with the approved revised plan reference G11/CP1/HSA03A deposited on the 23rd May 2013. The parking spaces shall be kept available for parking in association with the development thereafter.

 

10.       No development shall commence on any part of  ...  view the full minutes text for item 34.

35.

Planning Delegation Panel Action Sheets pdf icon PDF 29 KB

Item for information.

Minutes:

RESOLVED:

 

To note the information.

36.

Future Applications pdf icon PDF 18 KB

Item for information.

Minutes:

RESOLVED:

 

To note the information.

37.

Any other items which the Chair considers urgent.

Minutes:

The Chair informed Members that two Judicial Review applications have been made in respect of recent Crematoria applications. Gedling Borough Council’s will defend the decision made by the Committee and Members will be updated in due course.