Development of the Gedling Country Park Heritage and Cultural Visitor Centre

13/05/2016 - Development of the Gedling Country Park Heritage and Cultural Visitor Centre

The purpose of this decision report is there for to record my decision to: 1. approve the use of the SCAPE framework agreement to deliver this particular design and build project. 2. approve the spend against the approved budget of £96,084,.54 to enable the SCAPE approved contractors, GF Tomlinson to undertake the pre construction works needed. 3. on the Council's behalf write to appoint GF Tomlinson, in accordance with the CDM regulations of 2015 to formally advising them that we consider them to be the Principal Contractor for the project. 4. appoint Nottingham City Councils internal specialist team to undertake for GBC the functions of Quantity Surveying, contract administration and our client CDM obligations.