Application No. 2018/0115 - Lakeside, Mansfield Road Bestwood

Minutes:

Proposed hotel.

 

The Service Manager – Development Services introduced the report.

 

During the debate, the Service Manager – Development Services suggested an additional condition requiring the proposed hotel to be ancillary to the leisure use in the former pumping station on site.

 

Members then proposed an amendment to the recommendation to include an additional condition and delegated authority to the Service Manager – Development Services to provide the appropriate wording. 

 

RESOLVED to agree the additional condition and delegate authority to the Service Manager – Development Services to provide the appropriate wording. 

 

RESOLVED:  Following referral to the Secretary of State Case Work Unit. That the Borough Council GRANTS FULL PLANNING PERMISSION, subject to the following conditions:  

 

Conditions

 

 1         The development must be begun not later than three years beginning with the date of this permission.

 

 2         The development hereby permitted shall be constructed strictly in accordance with the Application Forms and the following approved plans submitted with the application: Heritage Statement (February 2018 - ref: PP1109); Planning Design and Access Statement (February 2018 - ref: PPS1109); Lakeside Eaves Detail (rec'd: 06.02.18); Site Location Plan; Floor Plans (ref: 970 - 1); Site Plan (ref: 970 - 3); Elevations (ref: 970 - 2); Sections (ref: 970 - 4); Streetscene (rec'd: 06.02.18); Preliminary Ecology Report (dated: 10th May 2018); Preliminary Ecological Appraisal (ref: OXF10939); Additional Information: Heritage Assets (Date: July 2018 - ref: PPS1109); and Flood Risk Assessment (ref: RCEF64439-002 R).

 

 3         Prior to the first use of the hereby approved Hotel details of the proposed improvements to the access on the A60 Mansfield Road, as shown for indicative purposes on drawing number 970-3 shall be submitted to and approved in writing by the Local Planning Authority. The submitted details shall include construction specification of the access, together with the re-location of street lighting column and signage near the entrance point. The works shall be implemented strictly in accordance with the approved details prior to the hotel being first brought into use.

 

 4         The Hotel shall not become operational until the parking, turning and servicing areas are surfaced in a bound material with the parking bays clearly delineated in accordance with drawing number 970-3. The parking, turning and servicing areas shall be maintained in the bound material for the life of the development and shall not be used for any purpose other than the parking, turning and loading and unloading of vehicles.

 

 5         Before development is commenced there shall be submitted into and approved in writing by the Local Planning Authority, (1) A tree protection plan to graphically show the locations of any tree and root protection barriers; (2) Arboricultural impact assessment identifying what impacts might arise from the proposed works; (3) Arboricultural Method Statement to give guidance on aspects of proposed works which were identified within the Arboricultural impact assessment. The AMS provides guidance as to how works might be mitigated or compensated for; (4) Details of any special engineering works and surfacing required near trees. The approved measures of protection shall be implemented strictly in accordance with the approved details for the duration of the construction period.

 

 6         Prior to any above ground works commencing on site there shall be submitted to and approved in writing by the Local Planning Authority full details of both soft and hard landscape works. The detailed landscape plans and particulars shall include: (a) details of size, species, positions and densities of all trees, hedges and shrubs to be planted; (b) precise details of the feature garden, rose border and trellis to the booster station; (c) the proposed means of surfacing access roads, car parking areas, roadways, and footpaths (d) a programme of implementation. (e) a landscape management plan, including long-term design objectives, management responsibilities and maintenance schedules for all landscape areas, and (f) details of any proposed external lighting to car parking areas and walkways. The development shall be implemented in accordance with the approved details, which shall be retained for the lifetime of the development.

 

 7         No above ground construction works shall commence until samples of the proposed materials to be used in the external construction of the development have been submitted to, and approved in writing by, the Local Planning Authority and the development shall only be undertaken in accordance with the materials so approved and shall be retained as such thereafter.

 

 8         Unless otherwise agreed by the Local Planning Authority, development must not commence until the following has been complied with: Site Characterisation: An assessment of the nature and extent of any potential contamination has been submitted to and approved in writing by the Local Planning Authority. This assessment must be undertaken by a competent person, and shall assess any contamination on the site, whether or not it originates on the site. Moreover, it must include; a survey of the extent, scale and nature of contamination and; and assessment of the potential risks to: human health, property, adjoining land, controlled waters, ecological systems, archaeological sites and ancient monuments. Submission of Remediation Scheme: Where required, a detailed remediation scheme (to bring the condition suitable for the intended use by removing unacceptable risks to critical receptors) should be submitted to and approved in writing by the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, an appraisal of remedial options, and proposal of the preferred option(s), and a timetable of works and site management procedures.

 

 9         In the event that remediation identified in the Remediation Scheme is required to render the development suitable for use, the agreed remediation scheme shall be implemented in accordance with the approved timetable of works. Prior to occupation of any building(s) a Verification Report (that demonstrates the effectiveness of the remediation carried out) must be submitted and approved in writing by the Local Planning Authority.

 

10        In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority and once the Local Planning Authority has identified the part of the site affected by the unexpected contamination development must be halted on that part of the site. Prior to the first occupation of the development an Assessment must be undertaken in accordance with the requirements above, and where remediation is necessary a remediation scheme, together with a timetable for its implementation and verification reporting, must be submitted to and approved in writing by the Local Planning Authority.

 

11        Before development commences details of reveals to be introduced within the brickwork of the building and to window openings shall be submitted to and approved in writing by the Local Planning Authority. The depth of reveals on the former Pumping Station shall be used for reference. The building shall be constructed in accordance with the approved details for the brickwork and window opening reveals.

 

12        Before above ground works commence a sample panel of the proposed brickwork, stonework and eaves details showing the proposed bond, mortar and joints to be used within these aspects and details of proposed downpipes and guttering shall be submitted to and approved in writing by the Local Planning Authority. The development shall be undertaken strictly in accordance with the approved details.

 

13        The development hereby permitted shall not commence until such time as a hydrogeological risk assessment has been submitted to, and approved in writing by the Local Planning Authority. The risk assessment should cover all aspects of the construction and operation of the development. The assessment must demonstrate how the integrity of the source will not be compromised by the foundation design and loading of the development. It should show how during construction site run off will not contaminate the boreholes and any fuel will be stored and transferred in such a way where it is not possible for contamination to enter the aquifer. The risk assessment will need to show that foul and surface water drainage will be managed in such a way that it is not possible for contamination to enter the aquifer and impact the source. The risk assessment should include a site management plan to identify how site personnel will manage the risk and any mitigation action that will be taken.

 

14        The development hereby permitted shall not commence until such time as a scheme for foundation design has been submitted to, and approved in writing by the Local Planning Authority. The scheme shall be implemented strictly in accordance with the approved details.

 

15        The development hereby permitted may not commence until a foul water drainage scheme has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented as approved and completed prior to the development being brought into use. Any foul drainage design must use best available technology to ensure that there is no risk of contamination entering the public drinking water system. Any discharge of effluent will require an environmental permit.

 

16        Prior to the commencement of development there shall be submitted to and approved in writing by the Local Planning Authority, details of a surface water drainage scheme for the site, based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the development. The surface water drainage scheme shall subsequently be implemented in accordance with the approved details and shall be retained for the lifetime of the development. No infiltration of surface water drainage into the ground is permitted other than with the written consent of the Local Planning Authority. Any proposed infiltrating drainage must adequately demonstrate that contaminated water will not enter the aquifer.

 

17        Before development has commenced there shall be submitted to and approved in writing a Bat Scoping Survey and Mitigation Strategy for the tree marked T4 on Appendix 1: Phase 1 Habitat Plan. Once approved the development shall be carried out strictly in accordance with the approved Bat Scoping Survey and Method Statement.

 

18        Before development has commenced there shall be submitted to and approved in writing an ecological mitigation and enhancement plan which accords with the recommendations of Section 5 - Preliminary Ecological Appraisal (Dated: April 2018). Once approved the development shall be constructed strictly in accordance with the approved details.

 

19        No development shall take place until a Construction Environmental Method Statement has been submitted to, and approved in writing by, the local planning authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide for: (i) the parking of vehicles of site operatives and visitors; (ii) loading and unloading of plant and materials; (iii) storage of plant and materials used in constructing the development; (iv) the erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate; (v) wheel washing facilities; (vi) measures to control the emission of dust and dirt during construction; (vii) a scheme for recycling/disposing of waste resulting from demolition and construction works.

 

20        Before development is commenced there shall be submitted to and approved in writing by the Borough Council details of a Local Employment Agreement to cover the construction of the development hereby permitted and the creation of new jobs in the local area.  The Local Employment Agreement shall be implemented strictly in accordance with the approved details, unless otherwise prior agreed in writing by the Local Planning Authority.

 

 

 

 

Reasons

 

 1         In order to comply with Section 51 of the Planning and Compulsory Purchase Act 2004.

 

 2         For the avoidance of doubt.

 

 3         To ensure works are carried out on the public highway prior to the Hotel opening.

 

 4         To ensure that adequate off-street parking provision is made to reduce the possibilities of the proposed development leading to on-street parking in the area.

 

 5         To minimise any potential impacts on biodiversity and the landscape in accordance with Section 11 of the National Planning Policy Framework and Policy 17 of the Aligned Core Strategy for Gedling Borough (September 2014).

 

 6         To ensure a satisfactory development and that the landscaping of the development accords with the requirements of  Policy 17 of the Aligned Core Strategy.

 

 7         To ensure a satisfactory standard of external appearance.

 

 8         To ensure that practicable and effective measures are taken to treat, contain or control any contamination and to protect controlled waters in accordance with the aims of LPD7 and LPD10.

 

 9         To ensure that practicable and effective measures are taken to treat, contain or control any contamination and to protect controlled waters in accordance with the aims of LPD7.

 

10        To ensure that practicable and effective measures are taken to treat, contain or control any contamination and to protect controlled waters in accordance with the aims of LPD7.

 

11        To ensure a satisfactory development that accords with Policy 10 of the Aligned Core Strategy.

 

12        To ensure a satisfactory development that accords with Policy 10 of the Aligned Core Strategy.

 

13        To protect controlled waters, the adjacent public water supply source, bore holes and underlying adit system in accordance with LPD7.

 

14        To ensure that the proposed development does damage the underlying drinking water supply source. The use of piled foundations will pose a much greater risk to the integrity of the underlying adit system and nearby borehole.

 

15        To protect controlled waters, the adjacent public water supply source, bore holes and underlying adit system in accordance with LPD7.

 

16        To protect controlled waters, the adjacent public water supply source, bore holes and underlying adit system in accordance with LPD7. Infiltration drainage inherently increases the risk of contamination entering the aquifer and water supply source.

 

17        To ensure that practicable and effective measures are taken to protect bats and their roosts during the construction of the development in accordance with LPD18.

 

18        To ensure that practicable and effective measures are taken to protect and mitigate against impacts on biodiversity and ecology in accordance with LPD18.

 

19        To protect the residential amenity of the area in accordance with the aims of Section 11 of the National Planning Policy Framework and Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014).

 

20        To seek to ensure that the development provides appropriate employment and training opportunities, in accordance with Policy 4 of the Aligned Core Strategy for Gedling Borough (September 2014).

 

Reasons for Decision

 

The development has been considered in accordance with the National Planning Policy Framework, the Aligned Core Strategy for Gedling Borough (September 2014) The Gedling Borough Replacement Local Plan (Certain Policies Saved 2014), and the Local Planning Document where appropriate.  In the opinion of the Borough Council, the proposed development largely accords with the relevant policies of these frameworks and plans.  Where the development conflicts with the Development Plan, it is the opinion of the Borough Council that other material considerations indicate that permission should be granted. The benefits of granting the proposal outweigh any adverse impact of departing from the Development Plan.

 

Notes to Applicant

 

Your attention is drawn to an informal planning guidance document which has been produced to try and define what sustainable development means in the context of air quality, and how to decrease levels by incorporating mitigation measures into scheme design as standard. (see: http://gedling.gov.uk/planningbuildingcontrol/planningpolicy/emerginglocalplan/supplementaryplanningdocuments/). It is therefore requested commitment to incorporate provision for an EV (electrical vehicle) charging point per dwelling; to allow future residents to charge electrical/hybrid vehicles into the future. Reference can be made to guidance produced by IET 'Code of Practice for EV Charging Equipment Installation' for details of charging points and plugs specifications.

 

The applicant is advised that all planning permissions granted on or after 16th October 2015  may be subject to the Community Infrastructure Levy (CIL). Full details of CIL are available on the Council's website.The proposed development has been assessed and it is the Council's view that CIL is not payable on the development hereby approved as the development type proposed is zero rated in this location.

 

No removal of hedgerows, trees or shrubs which have the potential to support nesting birds shall take place between 1st March and 31st August inclusive, unless a competent ecologist has undertaken a careful, detailed check for active birds' nests immediately before clearance works commence and provided written confirmation that no birds will be harmed and/or that there are appropriate measures in place to protect nesting bird interest on site. Any such written confirmation should be submitted to the local planning authority. As you will be aware all birds, their nests and eggs (except pest species) are protected by the Wildlife and Countryside Act 1981 (and as amended).

 

Planning Statement - The Borough Council has worked positively and proactively with the applicant in accordance with paragraph 38 of the National Planning Policy Framework (2018). Negotiations have taken place during the determination of the application to address adverse impacts identified by officers. Amendments have subsequently been made to the proposal, addressing the identified adverse impacts, thereby resulting in a more acceptable scheme and a favourable recommendation.

 

The proposed development lies within a coal mining area which may contain unrecorded coal mining related hazards. If any coal mining feature is encountered during development, this should be reported immediately to The Coal Authority on 0845 762   6848. Further information is also available on The Coal Authority website at www.coal.decc.gov.uk.Property specific summary information on past, current and future coal mining activity can be obtained from The Coal Authority's Property Search Service on 0845 762 6848 or at www.groundstability.com.

 

 

 

 

 