Agenda item

Planning Application 2017/0155 - Brookfields Garden Centre, Mapperley Plains, Arnold

Minutes:

Outline application for the erection of up to 32 dwellings, including access.

 

Simon Mandeville, a local resident, spoke in objection to the application.

 

The Service Manager – Development Services informed Members that further to the publication of the report, a petition signed by 146 residents had been received raising objection to the application on the grounds that a decision should not be made until the North East Arnold Development Brief was finalised, the unsuitability of the proposed access to the site on Crawford Rise, the access to the adjacent site from Crawford Rise, that wildlife in native hedgerows must be retained and that the petition should be debated at a meeting of Full Council.

 

The Service Manager – Development Services informed Members that in addition to the petition, one further letter of objection had been received in relation to highway safety and particularly parked cars.

 

The Service Manager – Development Services recommended that the Borough Council should grant outline planning permission in accordance with the report but with an amendment to the recommendation at paragraph 16 to require the Section 106 Agreement to also require affordable housing in accordance with paragraph 13.1.

 

 

RESOLVED to GRANT OUTLINE PLANNING PERMISSION, with matters relating to Appearance, Landscaping, Layout and Scale reserved for subsequent approval and subject to the applicant entering into a Section 106 Agreement with the Borough Council as local planning authority and with the County Council education authority and highways authority for the provision of, or financial contributions towards Educational Facilities, Healthcare, Local Employment Agreement, Bus Stop Improvements and Public Open Space; and subject to the following conditions:   

 

Conditions

 

 1         Approval of the details of Appearance, Landscaping, Layout and Scale (hereinafter called "the reserved matters") shall be obtained from the Local Planning Authority before the commencement of any development.

 

 2         Application for the approval of reserved matters must be made not later than three years from the date of the outline permission and the development to which this permission relates must be begun within two years from the date of final approval of reserved matters.

 

 3         The submission of all reserved matters and the implementation of the development shall be carried out in substantial accordance with the plans and documents received on the 2nd February 2017: - Application Forms; Planning Statement (January 2017); M-EC Transport Statement (Dec 2016); Topographical Survey; Design and Access Statement; Illustrative Masterplan (MI1039/003A); Extended Phase 1 Habitat Survey (P1198/1116/01); Constraints and Opportunities Plan; Site Location Plan; Minerals Resource Assessment; and Flood Risk Assessment (22362/01-17/4560).

 

 4         No part of the development hereby permitted shall take place until details of the new roads have been submitted to and approved in writing by the Local Planning Authority including longitudinal and cross sectional gradients, street lighting, drainage and outfall proposals, construction specification, provision of and diversion of utilities services, and any proposed structural works. The development shall be implemented in accordance with these details to the satisfaction of the Local Planning Authority.

 

 5         No part of the development hereby permitted shall be brought into use until all drives and parking areas are surfaced in a bound material (not loose gravel). The surfaced drives and parking areas shall then be maintained in such bound material for the life of the development.

 

 6         No part of the development hereby permitted shall be brought into use until the access driveways and parking areas are constructed with provision to prevent the unregulated discharge of surface water from the driveways and parking areas to the public highway. The provision to prevent the unregulated discharge of surface water to the public highway shall then be retained for the life of the development.

 

 7         In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority and once the Local Planning Authority has identified the part of the site affected by the unexpected contamination development must be halted on that part of the site.  An assessment must be undertaken in accordance with the requirements above and, where remediation is necessary, a remediation scheme, together with a timetable for its implementation and verification reporting, must be submitted to and approved in writing by the Local Planning Authority. The Remediation Scheme shall be implemented as approved.

 

 8         In the event that remediation is required to render the development suitable for use, a written remediation scheme and timetable of works shall be submitted to and approved in writing by the Local Planning Authority.  The scheme shall then be implemented in accordance with the approved details.  Prior to the development being first brought into use, a Verification Report (that satisfactorily demonstrates the effectiveness of the remediation carried out and identifying any requirements for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action) must be submitted to and approved in writing by the Local Planning Authority.

 

 9         No development shall take place until a Construction Environmental Method Statement has been submitted to, and approved in writing by, the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide for: (i) the parking of vehicles of site operatives and visitors; (ii) loading and unloading of plant and materials; (iii) storage of plant and materials used in constructing the development; (iv) the erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate; (v) wheel washing facilities; (vi) measures to control the emission of dust and dirt during construction; (vii) a scheme for recycling/disposing of waste resulting from demolition and construction works.

 

10        Before development is commenced there shall be submitted to and approved in writing by the Local Planning Authority, details of a surface water drainage scheme for the site, based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the development and based on the submitted Document: MEC Proposed Residential Development, Brookfields Garden Centre, Mapperley Plains, Flood Risk Assessment - January 2017 Report ref (22362/01-17/4560).  The scheme shall subsequently be implemented in accordance with the approved details before the development is completed and shall be retained for the lifetime of the development.

 

11        Before development is commenced there shall be submitted into and approved in writing by the Local Planning Authority, (1) A tree / hedge protection plan to graphically show the locations of any tree / hedge and root protection barriers; (2) Arboricultural impact assessment identifying what impacts might arise from the proposed works; (3) Arboricultural Method Statement (AMS). The AMS provides guidance as to how works might be mitigated or compensated for; (3) Details of any special engineering works and surfacing required near trees / hedges. The approved measures of protection shall be implemented in accordance with the approved details for the duration of the construction period.

 

12        Before development is commenced, there shall be submitted to and approved in writing by the Local Planning Authority a Desktop Study for Existing Ecological Information, to include: (1) Consultation with the Nottinghamshire Biological and Geological Records Centre (NBGRC); (2) An Extended phase 1 Habitat Survey; and (3) Details of avoidance, mitigation and compensation measures, and opportunities for enhancements. The development shall be implemented strictly in accordance with the approved details.

 

13        The detailed plans and particulars to be submitted as reserved matters in relation to scale shall include details of existing and proposed site levels in relation to adjacent properties. The development shall be implemented in accordance with the approved details.

 

14        The detailed plans and particulars to be submitted as reserved matters in relation to appearance shall include details of the materials to be used in the external elevations and roofs of the proposed buildings.  The development shall be carried out in accordance with the approved details, which shall be retained for the lifetime of the development.

 

15        The detailed plans and particulars to be submitted as reserved matters in relation to landscaping shall include: (a) details of the size, species, positions and density of all trees and shrubs to be planted, which shall consist of native species, ideally of local provenance, where possible; (b) details of the boundary treatments, including those to individual plot boundaries; (c) the proposed means of surfacing access roads, car parking areas, roadways and the frontages of properties such as driveways and footpaths to front doors and (d) a programme of implementation. The development shall be implemented in accordance with the approved details, which shall be retained for the lifetime of the development.

 

16        If within a period of five years beginning with the date of the planting of any tree or shrub, approved as reserved matters in relation to landscaping, that tree or shrub, or any tree or shrub that is planted in replacement of it, is removed, uprooted or destroyed or dies, or becomes in the opinion of the Local Planning Authority seriously damaged or defective, another tree or shrub of the same species and size as that originally planted shall be planted at the same place.

 

Reasons

 

 1         To comply with the requirements of Section 92 of the Town and Country Planning Act 1990. The application is expressed to be in outline only in accordance with Article 5 of the Town and Country Planning (Development Management Procedure)(England) Order 2015.

 

 2         To comply with the requirements of Section 92 of the Town and Country Planning Act 1990.

 

 3         For the avoidance of doubt.

 

 4         To ensure the development is constructed to adoptable standards.

 

 5         To reduce the possibility of deleterious material being deposited on the public highway (loose stones etc.)

 

 6         To ensure surface water from the site is not deposited on the public highway causing dangers to road users.

 

 7         To ensure that practicable and effective measures are taken to treat, contain or control any contamination and to protect controlled waters in accordance with the aims of LPD7.

 

 8         To ensure that practicable and effective measures are taken to treat, contain or control any contamination and to protect controlled waters in accordance with the aims of LPD7.

 

 9         To protect the residential amenity of the area in accordance with the aims of Section 11 of the National Planning Policy Framework and Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014).

 

10        To prevent the increased risk of flooding; to improve and protect water quality; to improve habitat and amenity; to ensure the future maintenance of the sustainable drainage structures; and to protect the water environment from pollution, in accordance with the National Planning Policy Framework, Policies 1 and 17 of the Aligned Core Strategy Submission Documents and Policy LPD4.

 

11        To minimise any potential impacts on biodiversity and the landscape in accordance with Section 11 of the National Planning Policy Framework, Policy 17 of the Aligned Core Strategy for Gedling Borough (September 2014) and Policy LPD18 (July 2018).

 

12        To minimise any potential impacts on biodiversity in accordance with Section 11 of the National Planning Policy Framework, Policy 17 of the Aligned Core Strategy for Gedling (September 2014) and Policy LPD18.

 

13        To ensure a satisfactory development in accordance with the aims of Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014).

 

14        To ensure a satisfactory development in accordance with the aims of Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014).

 

15        To ensure that the landscaping of the proposed development accords with Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014).

 

16        To ensure that the landscaping of the proposed development accords with Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014).

 

Reasons for Decision

 

The development has been considered in accordance with the National Planning Policy Framework, the Aligned Core Strategy for Gedling Borough (September 2014) and the Local Planning Document (July 2018), where appropriate. In the opinion of the Borough Council, the proposed development largely accords with the relevant policies of these frameworks and plans.  Where the development conflicts with the Development Plan, it is the opinion of the Borough Council that other material considerations indicate that permission should be granted. The benefits of granting the proposal outweigh any adverse impact of departing from the Development Plan.

 

Notes to Applicant

 

It is an offence under S148 and S151 of the Highways Act 1980 to deposit mud on the public highway and as such you should undertake every effort to prevent it occurring.

 

The applicant should note that notwithstanding any planning permission that if any highway forming part of the development is to be adopted by the Highways Authority. The new roads and any highway drainage will be required to comply with the Nottinghamshire County Council's current highway design guidance and specification for roadworks.

 

The Advanced Payments Code in the Highways Act 1980 applies and under section 219 of the Act payment will be required from the owner of the land fronting a private street on which a new building is to be erected.  The developer should contact the Highway Authority with regard to compliance with the Code, or alternatively to the issue of a Section 38 Agreement and bond under the Highways Act 1980.  A Section 38 Agreement can take some time to complete. Therefore, it is recommended that the developer contact the Highway Authority as early as possible.

 

It is strongly recommended that the developer contact the Highway Authority at an early stage to clarify the codes etc. with which compliance will be required in the particular circumstance, and it is essential that design calculations and detailed construction drawings for the proposed works are submitted to and approved by the County Council (or District Council) in writing before any work commences on site.

 

In order to carry out the off-site works required you will be undertaking work in the public highway which is land subject to the provisions of the Highways Act 1980 (as amended) and therefore land over which you have no control. In order to undertake the works you will need to enter into an agreement under Section 278 of the Act. All correspondence with the Highway Authority should be addressed to: TBH - NCC (Highways Development Control) (Floor 8), Nottinghamshire County Council, County Hall, Loughborough Road, West Bridgford, Nottingham, NG2 7QP.

 

No removal of hedgerows, trees or shrubs shall take place on site during the bird nesting season (1st March to 31st August inclusive in any given year), unless pre-commencement checks for nesting birds have been undertaken by an appropriately qualified ecologist and the outcome reported to the Borough Council.

 

The Environment Agency advises that SuDS involve a range of techniques, including methods appropriate to impermeable sites that hold water in storage areas e.g. ponds, basins, green roofs etc rather than just the use of infiltration techniques. Support for the SuDS approach is set out in NPPF.

 

The proposed development lies within a coal mining area which may contain unrecorded coal mining related hazards. If any coal mining feature is encountered during development, this should be reported immediately to The Coal Authority on 0845 762   6848. Further information is also available on The Coal Authority website at www.coal.decc.gov.uk.Property specific summary information on past, current and future coal mining activity can be obtained from The Coal Authority's Property Search Service on 0845 762 6848 or at www.groundstability.com.

 

The Borough Council has worked positively and proactively with the applicant, in accordance with paragraphs 38 of the National Planning Policy Framework, based on seeking solutions to problems arising in relation to dealing with the planning application.

 

The applicant is advised that all planning permissions granted on or after 16th October 2015 may be subject to the Community Infrastructure Levy (CIL). Full details of CIL are available on the Council's website. The proposed development has been assessed and it is the Council's view that CIL IS PAYABLE on the development hereby approved.  The actual amount of CIL payable will be calculated when a decision is made on the subsequent reserved matters application.

 

The Environment Agency advises that surface water run-off should be controlled as near to its source as possible through a sustainable drainage approach to surface water management.  Sustainable Drainage Systems (SuDS) are an approach to managing surface water run-off which seeks to mimic natural drainage systems and retain water on-site, as opposed to traditional drainage approaches which involve piping water off-site as quickly as possible.

 

 

 

 

Supporting documents: