Agenda item

Application Number 2014/0273 - Land at Corner of Longdale Lane and Kighill Lane, Ravenshead

Minutes:

Outline Planning Permission for up to 31 No. dwellings with all matters reserved.

 

The Service Manager – Development Services advised Members that further to the publication of the report, the NHS Mansfield and Ashfield Clinical Commissioning Group would not be seeking a contribution.

 

The Service Manager – Development Services therefore proposed an amendment to the recommendation in order to remove the requirement for the applicant to enter into a section 106 for the provision of, or financial contribution towards Healthcare facilities. 

 

RESOLVED:

 

That the Borough Council GRANTS OUTLINE PLANNING PERMISSION, subject to the applicant entering into a Section 106 Agreement with the Borough Council as local planning authority and with the County Council as local highway and education authority for the provision of, or financial contributions towards, Affordable Housing,Local Labour Agreement, Transport Infrastructure Improvements, Open Space, Management Company and Educational Facilities; and subject to the following conditions:   

 

Conditions

 

 1         Approval of the details of Access, Appearance, Landscaping, Layout and Scale (hereinafter called "the reserved matters") shall be obtained from the Local Planning Authority before the commencement of any development.

 

 2         Application for the approval of reserved matters must be made not later than three years from the date of the outline permission and the development to which this permission relates must be begun within two years from the date of final approval of reserved matters.

 

 3         The detailed plans and particulars to be submitted as reserved matters in relation to scale shall include details of existing and proposed site levels in relation to adjacent properties.  The development shall be implemented in accordance with the approved details, unless otherwise prior agreed in writing by the Local Planning Authority.

 

 4         No development shall commence on any part of the application site unless or until a detailed design of the major / minor T junction, as shown for indicative purposes on the illustrative layout has been submitted for approval.

 

 5         No part of the development hereby permitted shall be brought into use until the visibility splays of 2.4m x 43m are provided in accordance with details to be first submitted and approved in writing by the Local Planning Authority. The area within the visibility splays referred to in this Condition shall thereafter be kept free of all obstructions, structures or erections exceeding 0.6metres in height.

 

 6         No part of the development hereby permitted shall be brought into use until a 2.00m wide footway has been provided across the site frontage on Longdale Lane, in accordance with details to be first submitted and approved in writing by the Local Planning Authority.

 

 7         The formal written approval of the Local Planning Authority is required prior to commencement of any development within the site curtilage with regard to parking and turning facilities, access widths, gradients, surfacing, street lighting, structures, visibility splays and drainage (hereinafter referred to as reserved matters.)

 

 8         Details of measures to prevent the deposit of debris upon the adjacent public highway shall be submitted and approved in writing by the Local Planning Authority prior to any works commencing on site. The approved measures shall be implemented prior to any other works commencing on site.

 

 9         No part of the development hereby permitted shall be occupied until a Travel Plan has been submitted to and approved in writing by the local planning authority. The Travel Plan shall set out proposals (including targets, a timetable and enforcement mechanism) to promote travel by sustainable modes which are acceptable to the local planning authority and shall include arrangements for monitoring of progress of the proposals. The Travel Plan shall be implemented in accordance with the timetable set out in that plan unless otherwise agreed in writing by the local planning authority.

 

10        A swept path for a Refuse lorry to turn and exit the site in a forward gear shall be submitted with the 'layout' reserved matter. The Refuse Lorry is an Elite 6 - 8x4MS wide Track (Euro 6 specifications).

 

11        No development shall take place until a Construction Environmental Method Statement has been submitted to, and approved in writing by, the local planning authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide for: (i) the parking of vehicles of site operatives and visitors; (ii) loading and unloading of plant and materials; (iii) storage of plant and materials used in constructing the development; (iv) the erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate; (v) wheel washing facilities; (vi) measures to control the emission of dust and dirt during construction; (vii) a scheme for recycling/disposing of waste resulting from construction works.

 

12        Before development is commenced there shall be submitted to and approved in writing by the Local Planning Authority details of a surface water drainage scheme for the site based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the development.  The scheme shall subsequently be implemented in accordance with the approved details before the development is completed and shall be retained for the lifetime of the development.  The scheme to be submitted shall demonstrate: (1) The utilisation of holding sustainable drainage techniques which incorporate at least two differing forms of SuDS treatment in accordance with Table 3.3 of CIRIA C697 'The SuDS Manual' prior to discharging from the site; (2) The limitation of surface water run-off to the equivalent Greenfield runoff rate; (3) The ability to accommodate surface water run-off on-site up to the critical 1 in 100 year event plus an appropriate allowance for climate change, based upon the submission of drainage calculations; and (4) Responsibility for the future maintenance of drainage features.

 

13        Before development is commenced there shall be submitted into and approved in writing by the Local Planning Authority an Arboricultural Impact Assessment and Mitigation Strategy. The mitigation strategy shall include (1) A Woodland Management Plan detailing (i) any crown thinning of the crowded tree stock and invasive sycamores within the Local Wildlife Site adjacent to the application site, and (ii) any tree, shrub or undergrowth removal within the designated Local Wildlife Site adjoining the application site; (2) A tree protection plan to graphically show the locations of any tree and root protection barriers; (3) Arboricultural impact assessment identifying what impacts might arise from the proposed works; (4) Arboricultural Method Statement to give guidance on aspects of proposed works which were identified within the Arboricultural impact assessment which provides guidance as to how works might be mitigated or compensated for; (4) Details of any special engineering works and surfacing required near trees. The approved measures of protection shall be implemented strictly in accordance with the approved details for the duration of the construction period.

 

14        No development shall take place until there has been submitted to and approved in writing by the Borough Council details of a 'bat friendly' lighting scheme to ensure that artificial lighting (including any construction site lighting and compound lighting), avoids illuminating boundary features such as hedgerows and other areas of retained or created habitat.  The scheme shall be implemented strictly in accordance with the approved details.

 

15        The detailed plans and particulars to be submitted as reserved matters in relation to ecology shall include a Phase 1: Habitat Survey and Ecological Assessment. Detail shall include a survey for reptiles on field margins. In particular the assessment shall include precise details of any mitigation measures required and measures of how any reptiles would be cleared sensitively prior to development. The mitigation measures shall be implemented strictly in accordance with the approved details before the development is first commenced.

 

16        The detailed plans and particulars to be submitted as reserved matters in relation to appearance shall include details of the materials to be used in the external elevations and roofs of the proposed buildings.  The development shall be carried out in accordance with the approved details, which shall be retained for the lifetime of the development, unless otherwise prior agreed in writing by the Borough Council.

 

17        The detailed plans and particulars to be submitted as reserved matters in relation to landscaping shall include: (a) details of the size, species, positions and density of all trees and shrubs to be planted, which shall consist of native species, ideally of local provenance, where possible; (b) details of any mitigation measures, compensatory habitat, or wildlife corridors; (c) details of the boundary treatments, including those to individual plot boundaries; (d) the proposed means of surfacing access roads, car parking areas, roadways and the frontages of properties such as driveways and footpaths to front doors and (e) a programme of implementation. The development shall be implemented in accordance with the approved details.

 

18        If within a period of five years beginning with the date of the planting of any tree or shrub, approved as reserved matters in relation to landscaping, that tree or shrub, or any tree or shrub that is planted in replacement of it, is removed, uprooted or destroyed or dies, or becomes in the opinion of the Borough Council seriously damaged or defective, another tree or shrub of the same species and size as that originally planted shall be planted at the same place.

 

19        Unless otherwise agreed by the Local Planning Authority, development must not commence until the following has been complied with: Site Characterisation: An assessment of the nature and extent of any potential contamination has been submitted to and approved in writing by the Local Planning Authority. This assessment must be undertaken by a competent person, and shall assess any contamination on the site, whether or not it originates on the site. Moreover, it must include; a survey of the extent, scale and nature of contamination and; and assessment of the potential risks to: human health, property, adjoining land, controlled waters, ecological systems, archaeological sites and ancient monuments. Submission of Remediation Scheme: Where required, a detailed remediation scheme (to bring the condition suitable for the intended use by removing unacceptable risks to critical receptors) should be submitted to and approved in writing by the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, an appraisal of remedial options, and proposal of the preferred option(s), and a timetable of works and site management procedures.

 

20        In the event that remediation is required to render the development suitable for use, the agreed remediation scheme shall be implemented in accordance with the approved timetable of works. Prior to occupation of any building(s) a Verification Report (That demonstrates the effectiveness of the remediation carried out) must be submitted and approved in writing by the Local Planning Authority.

 

21        In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority and once the Local Planning Authority has identified the part of the site affected by the unexpected contamination development must be halted on that part of the site. An Assessment must be undertaken in accordance with the requirements above, and where remediation is necessary a remediation scheme, together with a timetable for its implementation and verification reporting, must be submitted to and approved in writing by the Local Planning Authority.

 

Reasons

 

 1         To comply with the requirements of Section 92 of the Town and Country Planning Act 1990. The application is expressed to be in outline only in accordance with Article 5 of the Town and Country Planning (Development Management Procedure)(England) Order 2015.

 

 2         To comply with the requirements of Section 92 of the Town and Country Planning Act 1990.

 

 3         To ensure a satisfactory development in accordance with the aims of Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014) and Policy ENV1 of the Gedling Borough Replacement Local Plan (Certain Policies Saved 2014).

 

 4         In the interest of highway safety.

 

 5         To ensure an adequate form of development in the interests of highway safety in accordance with Policy LPD35.

 

 6         To ensure an adequate form of development in the interests of highway safety in accordance with Policy LPD35.

 

 7         To ensure an adequate form of development in the interests of highway safety in accordance with Policy LPD35.

 

 8         In the interest of Highway Safety.

 

 9         To ensure an adequate form of development in the interests of highway safety in accordance with Policy LPD35.

 

10        To ensure an adequate form of development in the interests of highway safety in accordance with Policy LPD35.

 

11        To protect the residential amenity of the area in accordance with the aims of Section 11 of the National Planning Policy Framework and Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014).

 

12        To prevent the increased risk of flooding; to improve and protect water quality; to improve habitat and amenity; to ensure the future maintenance of the sustainable drainage structures; and to protect the water environment from pollution, in accordance with the National Planning Policy Framework and  Policies 1 and 17 of the Aligned Core Strategy Submission Documents.

 

13        To minimise any potential impacts on biodiversity and the landscape in accordance with Section 11 of the National Planning Policy Framework, Policy 17 of the Aligned Core Strategy for Gedling Borough (September 2014), and LPD18.

 

14        To minimise any potential impacts on biodiversity in accordance with Section 11 of the National Planning Policy Framework and Policy 17 of the Aligned Core Strategy for Gedling (September 2014).

 

15        To minimise any potential impacts on biodiversity in accordance with Section 11 of the National Planning Policy Framework, Policy 17 of the Aligned Core Strategy for Gedling (September 2014), and LPD18.

 

16        To ensure a satisfactory development in accordance with the aims of Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014) and Policy ENV1 of the Gedling Borough Replacement Local Plan (Certain Policies Saved 2014).

 

17        To ensure that the landscaping of the proposed development accords with Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014) and Policy ENV1 of the Gedling Borough Replacement Local Plan (Certain Policies Saved 2014).

 

18        To ensure a satisfactory development, in accordance with Policy 10 of the Aligned Core Strategy for Gedling Borough (September 2014) and Policy ENV1 of the Gedling Borough Replacement Local Plan (Certain Policies Saved 2014).

 

19        To ensure that practicable and effective measures are taken to treat, contain or control any contamination and to protect controlled waters in accordance with the aims of LPD7.

 

20        To ensure that practicable and effective measures are taken to treat, contain or control any contamination and to protect controlled waters in accordance with the aims of LPD7.

 

21        To ensure that practicable and effective measures are taken to treat, contain or control any contamination and to protect controlled waters in accordance with the aims of LPD7.

 

 

 

 

Reasons for Decision

 

The development has been considered in accordance with the National Planning Policy Framework, the Aligned Core Strategy for Gedling Borough (September 2014) The Gedling Borough Replacement Local Plan (Certain Policies Saved 2014), and the Local Planning Document Part 2 where appropriate.  In the opinion of the Borough Council, the proposed development largely accords with the relevant policies of these frameworks and plans.  Where the development conflicts with the Development Plan, it is the opinion of the Borough Council that other material considerations indicate that permission should be granted.  The benefits of granting the proposal outweigh any adverse impact of departing from the Development Plan.

 

Notes to Applicant

 

The applicant should note that notwithstanding any planning permission that if any highway forming part of the development is to be adopted by the Highways Authority. The new roads and any highway drainage will be required to comply with the Nottinghamshire County Council's current highway design guidance and specification for roadworks.

 

It is strongly recommended that the developer contact the Highway Authority at an early stage to clarify the codes etc. with which compliance will be required in the particular circumstance, and it is essential that design calculations and detailed construction drawings for the proposed works are submitted to and approved by the County Council (or District Council) in writing before any work commences on site.

 

In order to carry out the off-site works required you will be undertaking work in the public highway which is land subject to the provisions of the Highways Act 1980 (as amended) and therefore land over which you have no control. In order to undertake the works you will need to enter into an agreement under Section 278 of the Act.All correspondence with the Highway Authority should be addressed to: TBH - NCC (Highways Development Control) (Floor 8), Nottinghamshire County Council, County Hall, Loughborough Road, West Bridgford, Nottingham, NG2 7QP.

 

The Environment Agency advises that surface water run-off should be controlled as near to its source as possible through a sustainable drainage approach to surface water management.  Sustainable Drainage Systems (SuDS) are an approach to managing surface water run-off which seeks to mimic natural drainage systems and retain water on-site, as opposed to traditional drainage approaches which involve piping water off-site as quickly as possible.

 

Advice regarding travel plans can be obtained from the Travel Plans Officer at Nottinghamshire County Council, County Hall, Loughborough Road, West Bridgford, Nottingham.

 

Planning Statement - The Borough Council has worked positively and proactively with the applicant in accordance with paragraph 38 of the National Planning Policy Framework (2018). Negotiations have taken place during the determination of the application to address adverse impacts identified by officers. Amendments have subsequently been made to the proposal, addressing the identified adverse impacts, thereby resulting in a more acceptable scheme and a favourable recommendation.

 

No removal of hedgerows, trees or shrubs which have the potential to support nesting birds shall take place between 1st March and 31st August inclusive, unless a competent ecologist has undertaken a careful, detailed check for active birds' nests immediately before clearance works commence and provided written confirmation that no birds will be harmed and/or that there are appropriate measures in place to protect nesting bird interest on site. Any such written confirmation should be submitted to the local planning authority. As you will be aware all birds, their nests and eggs (except pest species) are protected by the Wildlife and Countryside Act 1981 (and as amended).

 

In order to carry out the off-site works required you will be undertaking work in the public highway which is land subject to the provisions of the Highways Act 1980 (as amended) and therefore land over which you have no control. In order to undertake the works you will need to enter into an agreement under Section 278 of the Act. Please contact the Highway Authority for details.

 

The proposed development lies within a coal mining area which may contain unrecorded coal mining related hazards. If any coal mining feature is encountered during development, this should be reported immediately to The Coal Authority on 0845 762   6848. Further information is also available on The Coal Authority website at www.coal.decc.gov.uk.Property specific summary information on past, current and future coal mining activity can be obtained from The Coal Authority's Property Search Service on 0845 762 6848 or at www.groundstability.com.

 

Date Recommended: 24th July 2018

 

Supporting documents: