Agenda item

Application No. 2017/1276 - Fairacre And 335 Mapperley Plains, Arnold.

Minutes:

Outline planning application for erection of 11 dwellinghouses with details of access, layout and scale and other matters reserved and demolition of two existing bungalows

Chris Norton, spoke in objection to the application, on behalf of local residents.

The Service Manager – Development Services introduced the report and recommended an additional condition requiring the submission of a Construction Environmental Management Plan to the Local Planning Authority prior to commencement of the development. 

The Service Manager – Development Services explained the reason for this additional condition was to protect the local environment.

 

RESOLVED that the Borough Council GRANTS OUTLINE PLANNING PERMISSION with matters relating to Appearance and Landscaping for subsequent approval, and subject to the following amended conditions:

 

Conditions

 

 1         Approval of the details of landscaping and appearance (hereinafter called "the reserved matters") shall be obtained from the Local Planning Authority before the commencement of any development.

 

 2         Application for the approval of reserved matters must be made not later than three years from the date of the outline permission and the development to which this permission relates must be begun within two years from the date of final approval of reserved matters.

 

 3         The submission of all reserved matters and the implementation of the development shall be carried out in substantial accordance with the plans and documents received on the 8th November 2018: - Application Forms; Design and Access Statement; Protected Species Survey; Tree Survey; Site Location Plan and the revised Layout Plan (ref: AS-17-01revE) received by the Local Planning Authority on 22nd May 2018.

 

 4         No part of the development hereby permitted shall take place until details of the new road have been submitted to and approved in writing by the Local Planning Authority including longitudinal and cross sectional gradients, visibility splays, street lighting, drainage and outfall proposals, construction specification, provision of and diversion of utilities services, and any proposed structural works. The development shall be implemented in accordance with these details to the satisfaction of the Local Planning Authority.

 

 5         No part of the development hereby permitted shall be brought into use until the visibility splays are provided in accordance with the approved plans ref (plan ref: AS-18-02 revA). The area within the visibility splays referred to in this condition shall thereafter be kept free of all obstructions for the life of the development.

 

 6         No part of the development hereby permitted shall be brought into use until all drives and parking areas are surfaced in a bound material (not loose gravel). The surfaced drives and parking areas shall then be maintained in such bound material for the life of the development.

 

 7         No part of the development hereby permitted shall be brought into use until the access driveways and parking areas are constructed with provision to prevent the unregulated discharge of surface water from the driveways and parking areas to the public highway. The provision to prevent the unregulated discharge of surface water to the public highway shall then be retained for the life of the development.

 

 8         No development hereby permitted shall commence until wheel washing facilities have been installed on the site in accordance with details first submitted to and approved in writing by the Local Planning Authority. The wheel washing facilities shall be maintained in working order at all times and shall be used by any vehicle carrying mud, dirt or other debris on its wheels before leaving the site so that no mud, dirt or other debris is discharged or carried on to a public road.

 

 9         Before development is commenced on site there shall be submitted to and approved in writing by the Borough Council, details of a surface water drainage scheme for the site, based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the development.  The scheme shall subsequently be implemented in accordance with the approved details before the development is completed and shall be retained for the lifetime of the development, unless otherwise prior agreed in writing by the Borough Council.

 

10        The detailed plans and particulars to be submitted to the Local Planning Authority as reserved matters in relation to landscaping shall include: (a) details of the size, species, positions and density of all trees and shrubs to be planted; (b) details of the boundary treatments, including those to individual plot boundaries; (c) the proposed means of surfacing access roads, car parking areas, roadways and the frontages of properties such as driveways and footpaths to front doors and (d) a programme of implementation. The development shall be implemented in accordance with the approved details, which shall be retained for the lifetime of the development, unless otherwise prior agreed in writing by the Borough Council.

 

11        If within a period of five years beginning with the date of the planting of any tree or shrub, approved as reserved matters in relation to landscaping, that tree or shrub, or any tree or shrub that is planted in replacement of it, is removed, uprooted or destroyed or dies, or becomes in the opinion of the Borough Council seriously damaged or defective, another tree or shrub of the same species and size as that originally planted shall be planted at the same place, unless otherwise prior agreed in writing by the Local Planning Authority.

 

12        In the event that contamination is found at any time when carrying out the approved development it must be reported in writing immediately to the Local Planning Authority and once the Local Planning Authority has identified the part of the site affected by the unexpected contamination development must be halted on that part of the site. An assessment must be undertaken in accordance with the requirements of the Local Planning Authority, and where remediation is necessary a remediation scheme, together with a timetable for its implementation and verification reporting, must be submitted to and approved in writing by the Local Planning Authority.

 

13        Notwithstanding the details contained within approved plan (Drawing Number: AS-17-01 rev E) the scale of the proposed dwelling(s), Type A and Type B as indicated on the plan, shall be restricted in their scale to either 2 storey dwellings or 2 storey dwellings with living accommodation built into the roof space.

 

14.       Prior to commencement of the development hereby approved a Construction Environmental Management Plan shall be submitted to and approved in writing by the Local Planning Authority.

 

Reasons

 

 1         To comply with the requirements of Section 92 of the Town and Country Planning Act 1990. The application is expressed to be in outline only in accordance with Article 5 of the Town and Country Planning (Development Management Procedure)(England) Order 2015.

 

 2         To comply with the requirements of Section 92 of the Town and Country Planning Act 1990.

 

 3         For the avoidance doubt.

 

 4         To ensure the development is constructed to adoptable standards.

 

 5         To maintain the visibility splays throughout the life of the development and in the interests of general Highway safety.

 

 6         To reduce the possibility of deleterious material being deposited on the public highway (loose stones etc.)

 

 7         To ensure surface water from the site is not deposited on the public highway causing dangers to road users.

 

 8         In the interests of Highway safety.

 

 9         To prevent the increased risk of flooding; to improve and protect water quality; to improve habitat and amenity; and to ensure the future maintenance of the sustainable drainage structures, in accordance with the National Planning Policy Framework and  Policies 1 and 17 of the Aligned Core Strategy Submission Documents.

 

10        To ensure a satisfactory development and that the landscaping of the development as proposed at reserved matters stage accords with Policy ENV1 and ENV2 of the Gedling Borough Replacement Local Plan (Certain Policies Saved 2008).

 

11        To ensure a satisfactory development and that the landscaping of the development as proposed at reserved matters stage accords with Policy ENV1 and ENV2 of the Gedling Borough Replacement Local Plan (Certain Policies Saved 2008).

 

12        To ensure that practicable and effective measures are taken to treat, contain or control any contamination and to protect controlled waters in accordance with the aims of Policies ENV1 and ENV3 of the Gedling Borough Replacement Local Plan (Certain Policies Saved 2008).

 

13        In the interests of the visual amenities and the character of the surrounding area.

 

14        To ensure appropriate measures are taken to protect the local environment.

 

Reasons for Decision

 

The development has been considered in accordance with the National Planning Policy Framework, the Aligned Core Strategy for Gedling Borough (September 2014) and the Gedling Borough Replacement Local Plan (Certain Policies Saved 2014), where appropriate.  In the opinion of the Borough Council, the proposed development largely accords with the relevant policies of these frameworks and plans.  Where the development conflicts with the Development Plan, it is the opinion of the Borough Council that other material considerations indicate that permission should be granted.  The benefits of granting the proposal outweigh any adverse impact of departing from the Development Plan.

 

Notes to Applicant

 

The Borough Council has worked positively and proactively with the applicant, in accordance with paragraphs 186 and 187 of the National Planning Policy Framework, based on seeking solutions to problems arising in relation to dealing with the planning application.  This has been achieved by meeting the applicant to discuss issues raised, providing details of issues raised in consultation responses; requesting clarification, additional information or drawings in response to issues raised; and providing updates on the application's progress.

 

It is an offence under S148 and S151 of the Highways Act 1980 to deposit mud on the public highway and as such you should undertake every effort to prevent it occurring.

 

This consent will require approval under Section 19 of the Nottinghamshire County Council Act 1985 and where the new streets are to be adopted an Agreement pursuant to Section 38 of the Highways Act 1980 will be required. Please contact Nottinghamshire County Council to ensure that approvals and agreements are secured before commencement of works.

 

The applicant should note that notwithstanding any planning permission that if any highway forming part of the development is to be adopted by the Highways Authority. The new roads and any highway drainage will be required to comply with the Nottinghamshire County Council's current highway design guidance and specification for roadworks.

 

The Advanced Payments Code in the Highways Act 1980 applies and under section 219 of the Act payment will be required from the owner of the land fronting a private street on which a new building is to be erected.  The developer should contact the Highway Authority with regard to compliance with the Code, or alternatively to the issue of a Section 38 Agreement and bond under the Highways Act 1980.  A Section 38 Agreement can take some time to complete. Therefore, it is recommended that the developer contact the Highway Authority as early as possible.

 

The applicant is advised that all planning permissions granted on or after 16th October 2015 may be subject to the Community Infrastructure Levy (CIL). Full details of CIL are available on the Council's website. The proposed development has been assessed and it is the Council's view that CIL IS PAYABLE on the development hereby approved.  The actual amount of CIL payable will be calculated when a decision is made on the subsequent reserved matters application.

 

The attached permission is for development which will involve building up to, or close to, the boundary of the site.  Your attention is drawn to the fact that if you should need access to neighbouring land in another ownership in order to facilitate the construction of the building and its future maintenance you are advised to obtain permission from the owner of the land for such access before beginning your development.

 

The Borough Council requests that the applicant considers incorporating provision for residential dwellings (with dedicated parking) to have dedicated outside electric power points, to allow residents to charge electric/hybrid vehicles into the future (see IET Code of Practice for EV Charging Equipment Installation).

 

The proposed development lies within a coal mining area which may contain unrecorded coal mining related hazards. If any coal mining feature is encountered during development, this should be reported immediately to The Coal Authority on 0845 762   6848. Further information is also available on The Coal Authority website at www.coal.decc.gov.uk.Property specific summary information on past, current and future coal mining activity can be obtained from The Coal Authority's Property Search Service on 0845 762 6848 or at www.groundstability.com.

 

Should any bat/s be found during demolition, work must stop immediately. If the bat/s does not voluntarily fly out, the aperture is to be carefully covered over to provide protection from the elements whilst leaving a small gap for the bat to escape should it so desire. The Bat Conservation Trust should be contacted immediately on (0845) 1300228 for further advice and they will provide a licensed bat worker to evaluate the situation and give advice. Failure to comply is an offence under the Wildlife and Countryside Act 1981 and the Conservation of Habitats and Species Regulations 2010 which makes it an offence to kill, injure or disturb a bat or to destroy any place used for rest or shelter by a bat (even if bats are not in residence at the time). The Countryside and Rights of Way Act 2000 strengthens the protection afforded to bats covering 'reckless' damage or disturbance to a bat roost.

 

Hours of construction including deliveries to the site shall be limited to: 7:30 to 18:00 Monday to Friday - 08:00 to 13:00 Saturday - No work shall be undertaken on Sundays or Public Holidays.

 

It is strongly recommended that the developer contact the Highway Authority at an early stage to clarify the codes etc. with which compliance will be required in the particular circumstance, and it is essential that design calculations and detailed construction drawings for the proposed works are submitted to and approved by the County Council (or District Council) in writing before any work commences on site. Highways Development Control Section, Highways South, Nottinghamshire County Council, County Hall floor 3, Loughborough Road, West Bridgford, Nottingham, NG2 7QP

 

Date Recommended: 22nd May 2018

 

 

 

Supporting documents: