Application No. 2013/0497- Land South Of Colwick Loop Road, Colwick, Nottinghamshire

Minutes:

Construction of A4 public house with restaurant facilities & associated managerial residential accommodation at first floor (full application) & A3 restaurant or A5 hot food takeaway (outline application).

 

The Service Manager, Planning and Economic Development, presented the report, which has been circulated prior to the meeting, and made Members aware of a letter of objection received by the department following publication of the report.

 

The Service Manager, Planning and Economic Development, also informed Members that, following comment from Nottinghamshire County Council after the publication of the report, there would no longer be a requirement for the applicant to enter into a Section 106 agreement towards travel plan monitoring.

 

RESOLVED to GRANT PLANNING PERMISSION subject to the following conditions:

 

Conditions

 

 1         The public house hereby permitted shall be begun within five years from the date of the approval of the last reserved matters to be approved in relation to the restaurant element.

 

 2         Application for the approval of any of the reserved matters (namely appearance, layout, landscaping and scale) required for the restaurant element shall be made to the Local Planning Authority before the expiration of three years from the date of this permission.

 

 3         The restaurant element hereby permitted shall be begun within five years from the date of the approval of the last reserved matters to be approved.

 

 4         The public house or restaurant element shall not be brought into use until either: a) The hazardous substances consents for both the Total Lindsey Oil Refinery Ltd and Chevron Ltd have been are revoked, or b) A report relating to the respective element has been submitted to the LPA outlining the level of risk posed by the presence of the Total Lindsey Oil Refinery Ltd together with details of any proposed mitigation measures and the LPA have agreed in writing that they are satisfied with the conclusions of the Report so to allow the respective element to be occupied. Any mitigation measures proposed in the report to be approved in writing by the Borough Council shall be implemented in accordance with the approved report.

 

 5         The restaurant element shall not exceed 452 square metres (Gross External Floor Area).

 

 6         The public house and restaurant shall be developed in accordance with drawings, A-PL-02 Rev. A (Location Plan) A-PL-30 B ( Marstons Public House and Restaurant Plan), 0055/12/ 02 02 C Site Plan,0055/12/ 02 04 C Elevations, 0055/12/ 02 05 B Fence Locations + Details and Pergola Details, 0055/12/ 02 03 A Floor and Roof Plan and Marstons Public House and Restaurant Detailed Planting Plan GC.818000.303 A.

 

 7         Prior to the public house being first brought into use precise details of the play equipment to be installed within the play area, together with a timescale for its installation shall be submitted to and approved in writing by the local planning authority. The play equipment shall be installed in accordance with the approved details and timescale, and shall be retained thereafter in accordance with the approved details.

 

 8         The approved planting scheme, fencing, pergola and surfacing materials to be used within the soft and hard landscaping scheme submitted in relation to the public house shall be provided prior to the to the public house being first brought into use, or to a timescale to be prior agreed in writing by the local planning authority. The fencing, pergola and surfacing materials shall be retained thereafter in accordance with the approved details.

 

 9         Prior to the public house being first brought into use precise details of any minor artefacts and structures such as external benches, refuse or storage units and lighting together with a timescale for their installation shall be submitted to and approved in writing by the local planning authority. Any proposed lighting scheme shall also include details of the spread of light beyond the site boundaries and the hours of illumination. Any minor artefacts or structures shall be installed in accordance with the approved details and retained thereafter.

 

10        The Public House shall not be brought into use until the parking/turning/servicing areas are provided in accordance with the approved plan 0055/12/0202 Rev C. The parking/turning/servicing areas shall not be used for any purpose other than purpose thereafter.

 

11        The Public House shall not be brought into use until the cycle parking layout as indicated on drawing 0055/12/0202 Rev C has been provided and that area shall not thereafter be used for any purpose other than the parking of cycles.

 

12        The Public House or Restaurant element shall not be occupied until a Full Travel Plan for that respective element has been submitted to and approved in writing by the local planning authority. The Travel Plan shall set out proposals (including targets, a timetable and enforcement mechanism) to promote travel by sustainable modes which are acceptable to the local planning authority and shall include arrangements for monitoring of progress of the proposals. The Travel Plan shall be implemented in accordance with the timetable set out in that plan unless otherwise agreed in writing by the Local Planning Authority.

 

13        Details of measures to prevent the deposit of debris upon the adjacent public highway during the construction of both the proposed Public House and Restaurant element shall be submitted to and approved in writing by the LPA prior to the commencement of development of the respective elements(excluding any site clearance and remediation works as required by condition 20). The approved measures shall be implemented in accordance with the approved details prior to any construction works commencing on the respective phase and retained in situ until the respective element has been constructed.

 

14        The proposed development shall not be brought into use until the following works have been provided in accordance with details that have been first agreed with the Local Highway Authority and shall be carried out to the satisfaction of the Local Planning Authority.; (a) A new signalised junction has been provided on to the Colwick Loop Road. (b) Highway Improvements have been provided at Colwick Loop Road / Road No1 junction. (c) Highway improvements have been provided at A612 / Burton Road / Shearing Hill junctions.

 

15        The Public House and Restaurant elements shall be carried out in accordance with the approved Flood Risk Assessment (FRA) and the following mitigation measures: (a) As a minimum, proposed floor levels will be set with a freeboard of 600mm above existing ground levels. (b) Other than in those areas where levelled or graded access is required to or from a building or to provide vehicular access into and between the respective elements, external finished ground levels will be no less than 300mm below the proposed floor level of the nearest building. (c) Where local flooding occurs surface water runoff is to be routed away from the buildings along the footways and roadways to the drainage system. The mitigation measures for each respective element shall be fully implemented prior to occupation of the respective element.

 

16        Prior to the commencement of development of the Public House or Restaurant elements (excluding any site clearance and remediation works as required by condition 20)  a scheme providing an evacuation plan for the respective element shall be submitted to, and approved in writing by, the local planning authority, in consultation with the Council's emergency planner.  The approved scheme for the respective element shall be fully implemented and subsequently maintained.

 

17        Prior to the commencement of development of the Public House or Restaurant elements (excluding any site clearance and remediation works as required by condition 20)  a scheme to provide flood resilience design for the respective element shall be submitted to, and approved in writing by, the local planning authority, in consultation with the Council's emergency planner.   The approved scheme for the respective element shall be fully implemented and subsequently maintained.

 

18        Prior to the commencement of development of the Public House or Restaurant elements (excluding any site clearance and remediation works as required by condition 20) a surface water drainage scheme for the respective element, based on sustainable drainage principles and an assessment of the hydrological and hydro geological context of the development, shall be submitted to and approved in writing by the local planning authority. The drainage strategy should demonstrate the surface water run-off generated up to and including the 1 in 100 year plus climate change critical storm will not exceed the run-off from the undeveloped site following the corresponding rainfall event. The respective scheme for each element shall subsequently be implemented in accordance with the approved details before the respective element is occupied. The scheme shall also include: (a) The utilisation of sustainable drainage techniques, including rainwater harvesting and permeable paving; (b) Limitation of the runoff rate to a 10% betterment from the existing drainage conditions as detailed in a letter dated 16th September 2013 from Morgan Tucker, limiting discharge to 5.3l/s/ha (QBAR); (c)Water quality management to incorporated within the design, with two forms of treatment prior to discharge from the site; (d) Demonstration through hydraulic calculations that appropriate attenuation is to be provided to limit the rate of runoff from the site.(e) Confirmation of responsibility and management of the drainage features on construction of the scheme.

 

19        Prior to the commencement of development of the Public House (excluding any site clearance and remediation works as required by condition 20)  a scheme for the safe refuge of any residents during an extreme event has been submitted to, and approved in writing by, the local planning authority, in consultation with the Council's emergency planner.  The scheme shall be fully implemented and subsequently maintained.

 

20        Prior to the commencement of development of the Public House or Restaurant elements (excluding any site clearance) an investigation and contamination risk assessment report relating to the respective element detailing those areas and / or contaminants not covered within the Ground Conditions Chapter of the submitted Environmental Statement shall be provided to the Local Planning Authority. If the information submitted with the application or within this additional report indicates that remediation is necessary, details of a remediation scheme for the respective element shall be submitted to and approved in writing by the Local Planning Authority. The remediation scheme shall include all works to be undertaken, remediation objectives and remediation criteria, a timetable of works and site management procedures and shall be carried out in accordance with the approved details and timetable of works. Written notification of the commencement of the remediation scheme shall be given to the local planning authority at least 2 weeks before the start of the remediation works and a validation report that demonstrates the effectiveness of the remediation carried out shall be submitted to and approved in writing by the local planning authority prior to the first occupation of the respective element. If during the course of development contamination not previously identified is found to be present at the site, no further development other than that agreed in writing with the Local Planning Authority shall be carried out until an amendment to the remediation scheme giving details on how to deal with this contamination has been submitted to and approved in writing by the Local Planning Authority. The remediation measures shall thereafter be carried out in accordance with the approved amended details.

 

21        Piling or any other foundation designs using penetrative methods shall not be permitted other than with the express written consent of the local planning authority, which may be given for those parts of the site where it has been demonstrated that there is no resultant unacceptable risk to groundwater. The development shall be carried out in accordance with the approved details.

 

22        The Public House and Restaurant element hereby approved shall not be brought into use until full details of a Local Employment Partnership has been submitted to and approved in writing by the Local Planning Authority, this shall include details of how the partnership shall be sustained for the life time of the development. The partnership shall be implemented in accordance with the approved details prior to either element being brought into use. Evidence shall be submitted to the Local Planning Authority that the partnership has been established.

 

23        Prior to occupation of either the public house element or the restaurant element a viability assessment for additional renewable energy installations shall be submitted to the Local Planning Authority. If these prove viable, including those producing power only for the site's use, full details of the proposed installations shall be submitted for the approval of the Local Planning Authority and installed until technologically obsolete.

Reasons

 

 1         To accord with Section 51 of the Planning and Compulsory Purchase Act 2004 and to allow sufficient time to enable either the revocation of the relevant Hazardous Substance Consents for Total Lindsey Oil Refinery Ltd and Chevron Ltd or for the Borough Council as Local Planning Authority to have confirmed in writing that the risk posed by the Total Lindsey Oil Refinery to be acceptable.

 

 2         To accord with Section 51 of the Planning and Compulsory Purchase Act 2004

 

 3         To accord with Section 51 of the Planning and Compulsory Purchase Act 2004

 

 4         The Borough Council as Local Planning Authority is not satisfied that the risk posed by the adjacent Total Lindsey Oil Refinery is acceptable to allow the occupation of the proposed public house/restaurant and the proposed drive through restaurant. This condition will enable the public house/restaurant and the proposed restaurant/takeaway to occupied only if the relevant hazardous substances consents for both the Total Lindsey Oil Refinery Ltd and Chevron Ltd have been revoked or if the Borough Council as Local Planning Authority has confirmed in writing that it is satisfied that the so as to allow  the development to be occupied whilst the adjacent Total Lindsey Oil Refinery is still in operation and the relevant hazardous substance consent for Chevron Ltd has been revoked.

 

 5         For the avoidance of doubt and to ensure that the gross external floor area of the unit is set at outline stage so that the impact of the proposed development is within the parameters indicated within the assessments that have accompanied the application.

 

 6         To ensure a satisfactory development that accords with Policy ENV1 of the Gedling Borough Replacement Local Plan.

 

 7         To ensure a satisfactory development that accords with Policy ENV1 of the Gedling Borough Replacement Local Plan.

 

 8         To ensure a satisfactory development that accords with Policy ENV2 of the Gedling Borough Replacement Local Plan.

 

 9         To ensure a satisfactory development that accords with Policy ENV2 of the Gedling Borough Replacement Local Plan.

 

10        In the interests of highway safety.

 

11        To encourage sustainable forms of transport

 

12        To encourage sustainable forms of transport .

 

13        In the interests of highway safety.

 

14        To ensure improve the capacity of the local highway network, in the interests of highway safety.

 

15        To reduce the risk of flooding to the proposed development.

 

16        To enable a safe means of egress from the site during an extreme flood event.

 

17        To reduce the impact of flooding on the development.

 

18        To prevent the increased risk of flooding, both on and off site and to manage surface water in a sustainable manner.

 

19        As living accommodation, ancillary to the use, is proposed then a safe refuge must be provided.

 

20        To ensure the site is suitable for use.

 

21        To ensure that there is no mobilisation/ migration of contamination into the underlying aquifer.

 

22        To ensure that the uses once operational employ local people.

 

23        To assist in satisfying energy demand from renewable energy sources, in line with paragraph 17 of the National Planning Policy Framework.

 

Reasons for Decision

 

The proposed development accords with the relevant policies of the Local Plan and the National Planning Policy Framework.

 

Notes to Applicant

 

For the purpose of the above conditions the following words and expressions shall be used, and unless otherwise stated elsewhere in the conditions shall have the following meaning: The proposed public house with dining facilities, managerial residential accommodation at first floor, car parking, landscaping and pedestrian access running east west between the retail element and the new access road comprise the "Public House". The proposed restaurant element to the south of the public house area is defined as the "Restaurant element".

 

For the purposes of this application the reference to details required prior to the commencement of development (except in relation to condition 20) shall exclude remediation works required under the remediation scheme approved under condition 20.

 

Your attention is drawn to the written comments of the Environment Agency, The Highway Authority, the Gedling Borough Council Scientific Officer, Network Rail and the Health and Safety Executive.

 

Planning Statement - The Borough Council has worked positively and proactively with the applicant in accordance with paragraphs 186 to 187 of the National Planning Policy Framework.

 