Minutes:
Variation of conditions 3 (approved drawings), 4 (highways) and 18 (trees) of planning permission 2020/0238 (An outline application for 11 new dwellings with matters of access, scale and layout under consideration).
The Principal Planning Officer introduced the report.
RESOLVED:
To GRANT PLANNING PERMISSION subject to the owner entering into planning obligations secured through a s106 agreement with the Borough Council as the Local Planning Authority to secure the long term maintenance of the road and subject to the following conditions for the reasons set out in the report.
Conditions
1 Details of appearance and landscaping (hereinafter called the reserved matters) for the development shall be submitted to and approved in writing by the Local Planning Authority before any development begins and the development shall be carried out as approved.
2 The application for the approval of reserved matters must be made not later the 11th August 2024 and the development to which this permission relates must be begun within two years from the date of the final approval of reserved matters.
3 This permission shall be read in accordance with the application form and following approved drawing: 153/A-NR-BJ/Pl-2 Rev D. The development shall thereafter be undertaken in accordance with these plans/details.
4 No dwelling hereby approved shall be occupied until a suitable access arrangement has been provided in accordance with the approved drawing no. 153/A-NR-BJ/Pl-2 Rev D.
5 No dwelling shall be occupied until the roads necessary to serve that dwelling have been constructed to base level.
6 No dwelling shall be occupied until all drives and parking areas are surfaced in a bound material (not loose gravel). The surfaced drives and parking areas shall then be maintained in such bound material for the life of the development.
7 Prior to the commencement of development details of the existing and proposed ground levels of the site and finished floor levels of the dwellings shall be submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be undertaken in accordance with the approved details.
8 No dwelling shall be occupied until one or more dedicated vehicle parking spaces and/ or a garage have been provided with access to an electric vehicle (EV) charge point. Charge points must have a minimum power rating output of 7kW on a dedicated circuit, capable of providing a safe overnight charge to an electric vehicle. All EV charging points shall meet relevant safety and accessibility requirements and be clearly marked with their purpose; which should be drawn to the attention of new residents in their new home welcome pack / travel planning advice.
9 Prior to commencement of the development a Construction Emission Management Plan (CEMP) for minimising the emission of dust and other emissions to air during the site preparation and construction shall be submitted to and approved in writing by the Local Planning Authority. The CEMP must be prepared with due regard to the guidance produced by the Council on the assessment of dust from demolition and construction and include a site specific dust risk assessment; all works on site shall, thereafter, be undertaken in accordance with the approved CEMP
10 The development shall be carried out in accordance with the submitted flood risk assessment (ref: Land at Ashdale, Nottingham Road, Burton Joyce, Gracemachin Planning and Property Ltd, Farrow Walsh Consulting, FW1907_FRA_001, V2.1, 06/04/2020) and the following mitigation measures it details: Finished floor levels shall be set no lower than 19.82 metres above Ordnance Datum (AOD) as stated within section 7.2.1 of the FRA. The mitigation measures shall then be fully implemented prior to occupation and subsequently in accordance with the scheme's timing/phasing arrangements. The measures detailed above shall be retained and maintained thereafter throughout the lifetime of the development.
11 No part of the development hereby approved shall commence until a detailed surface water drainage scheme based on the principles set forward by the approved Flood Risk Assessment (FRA) and Drainage Strategy, has been submitted to and approved in writing by the Local Planning Authority in consultation with the Lead Local Flood Authority. The scheme shall be implemented in accordance with the approved details prior to the first occupation of any dwelling. The scheme to be submitted shall: - Demonstrate that the development will use SuDS throughout the site as a primary means of surface water management and that design is in accordance with CIRIA C753. - Limit the discharge rate generated by all rainfall events up to the 100 year plus 40% (for climate change) critical rain storm 5 l/s rates for the developable area. - Provision of surface water run-off attenuation storage in accordance with 'Science Report SCO30219 Rainfall Management for Developments' and the approved FRA - Provide detailed design (plans, network details and calculations) in support of any surface water drainage scheme, including details on any attenuation system, and the outfall arrangements. Calculations should demonstrate the performance of the designed system for a range of return periods and storm durations inclusive of the 1 in 1 year, 1 in 2 year, 1 in 30 year, 1 in 100 year and 1 in 100 year plus climate change return periods. - For all exceedance to be contained within the site boundary without flooding new properties in a 100year+40% storm. - Details of STW approval for connections to existing network and any adoption of site drainage infrastructure. - Evidence of how the on-site surface water drainage systems shall be maintained and managed after completion and for the lifetime of the development.
12 Before development is commenced there shall be submitted to and approved in writing by the Local Planning Authority drainage plans for the proposed means of disposal of foul sewage. The scheme shall be implemented in accordance with the approved details before the development is first brought into use and shall be retained for the lifetime of the development thereafter.
13 In the event that contamination is found at any time when carrying out the approved development it must be reported in writing immediately to the Local Planning Authority and once the Local Planning Authority has identified the part of the site affected by the unexpected contamination development must be halted on that part of the site. An assessment must be undertaken in accordance with the requirements of the Local Planning Authority, and where remediation is necessary a remediation scheme, together with a timetable for its implementation and verification reporting, must be submitted to and approved in writing by the Local Planning Authority.
14 Development shall be undertaken in accordance with the approved noise report, completed by BSP Consulting, BSP Document Ref: RDBJ-BSP-ZZ-XX-RP-C-001-P1_Environmental_Noise_Assessment and the mitigation therein, notably with regard to window details and ventilation to the dwellings and fencing to the garden areas. Verification that the approved sound insulation has been implemented and is fully operational shall be submitted to and be approved in writing by the Local Planning Authority.
15 Development shall be undertaken in accordance with the Ecological Appraisal Report by JJH Consulting Ltd dated December 2019 and the recommendations and mitigation measures adhered to at all times.
16 Prior to the commencement of development, a further badger survey of the site shall be submitted and approved in writing by the Local Planning Authority. Any mitigation contained in the approved report shall thereafter be implemented.
17 Prior to the commencement of development, Great Crested Newt presence/absence surveys shall be submitted and approved in writing by the Local Planning Authority. Any mitigation contained in the approved report shall thereafter be implemented.
18 The development shall be undertaken in accordance with the Arboricultrural Report submitted as part of this Section 73 application and Impact Assessment by AWA Tree Consultants, dated August 2020, Reference AWA2971 and the Arboricultural Method Statement by AWA Tree Consultants, dated August 2020 reference AWA3363 submitted as part of the outline application, specific attention shall be given to the timings of events from arboricultural works through erection of protective fencing and development to protective fence removal and the need for strict monitoring throughout the process. The protective fencing shall be provided before site preparation commences and the protective fencing shall remain in place at all times during site preparation and development. The protective fencing shall only be removed following completion of the development.
19 Prior to the erection of any external lighting (other than within the curtilages of the approved dwellings) there shall be submitted to and approved in writing by the Local Planning Authority details of all such lighting, including levels of illumination and a lux plot of the estimated luminance. The external lighting shall be provided in accordance with the approved details and shall be retained as such thereafter for the lifetime of the development.
20 No above ground construction works shall commence until details of bat and bird boxes to be incorporated within the fabric of the buildings and/or within the site have been submitted to and approved in writing by the Local Planning Authority. The bat and bird boxes shall thereafter be provided prior to the first occupation of the development hereby approved.
21 No part of the development hereby permitted shall take place until details of the new road have been submitted to and approved in writing by the Local Planning Authority including longitudinal and cross-sectional gradients, visibility splays, street lighting, drainage and outfall proposals, construction specification, provision of and diversion of utilities services, and any proposed structural works. The development shall be implemented in accordance with the approved details and retained thereafter for the life of the development.
22 All access driveways and parking areas shall be constructed with provision to prevent the unregulated discharge of surface water from the driveways and parking areas to the public highway. The provision to prevent the unregulated discharge of surface water to the public highway shall then be retained for the life of the development.
23 No development hereby permitted shall commence until details of wheel washing facilities have been submitted to and approved in writing by the Local Planning Authority. The wheel washing facilities thereby approved shall be maintained in working order for the duration of the construction works at all times and shall be used by any vehicle carrying mud, dirt or other debris on its wheels before leaving the site so that no mud, dirt or other debris is discharged or carried on to a public road.
Reasons
1 To comply with the provision of Section 92(2) of the Town and Country Planning Act 1990.
2 To comply with the requirements of Section 51 of the Planning and Compulsory Purchase Act 2004.
3 For the avoidance of doubt.
4 To ensure an adequate form of development in the interests of highway safety and to comply with policy LPD61.
5 To ensure that each dwelling has appropriate vehicular access and to comply policy LPD61.
6 To ensure that loose material does not enter the highway and to comply with policy LPD61.
7 This pre-commencement condition is necessary to ensure that the development does not have a detrimental impact upon visual amenity or upon the occupiers of adjacent dwellings.
8 To ensure the development is constructed in an appropriate sustainable manner which takes into consideration air quality with in the Borough, and takes into consideration the National Planning Policy Framework and policy LPD11 of the Councils Local Plan.
9 To ensure the development is constructed in an appropriate sustainable manner which takes into consideration air quality with in the Borough, and takes into consideration the National Planning Policy Framework and policy LPD11 of the Councils Local Plan.
10 To ensure that the site is safe and suitable for use, thereby taking into consideration the aims of the National Planning Policy Framework 2021 (NPPF), policy 1 of the Aligned Core Strategy 2014 and policy LPD3 of the Local Planning Document 2018.
11 A detailed surface water management plan is required to ensure that the development is in accordance with National Planning Policy Framework 2021 and local planning policies. It should be ensured that all major developments have sufficient surface water management, are not at increased risk of flooding and do not increase flood risk off-site.
12 To ensure foul water is adequately disposed of and to comply with policies LPD4, LPD5 and LPD6.
13 To ensure the development is safe and suitable for use, thereby taking into consideration paragraph 121 of the National Planning Policy Framework and policy LPD7 of the Councils Local Plan.
14 To ensure that amenity of proposed dwellings are suitably protected and to comply with guidance within the NPPF.
15 To ensure that protected species are not detrimentally impacted and to comply with guidance within the NPPF.
16 To ensure that protected species are not detrimentally impacted and to comply with guidance within the NPPF.
17 To ensure that protected species are not detrimentally impacted and to comply with guidance within the NPPF.
18 To ensure that the trees to be retained at the site are appropriately protected at all times.
19 In the interests of protecting ecological interests.
20 No above ground construction works shall commence until details of bat and bird boxes to be incorporated within the fabric of the buildings and/or within the site have been submitted to and approved in writing by the Local Planning Authority. The bat and bird boxes shall thereafter be provided prior to the first occupation of the development hereby approved.
21 To ensure the development is constructed to an acceptable standard.
22 In the interests of highway safety.
23 In the interests of highway safety.
Reasons for Decision
The principle of the development accords with the objectives of national and local planning policies. It is considered that the site could be used for residential development without causing undue harm to visual and residential amenity, highway safety, ecological interests or flooding. It is therefore considered that the granting of outline planning permission would fully accord with the objectives of the relevant planning policies set out in the National Planning Policy Framework, Aligned Core Strategy, Local Planning Document and Supplementary Planning Documents.
Notes to Applicant
It is an offence under S148 and S151 of the Highways Act 1980 to deposit mud on the public highway and as such you should undertake every effort to prevent it occurring.The applicant should note that notwithstanding any planning permission if any highway forming part of the development is to be adopted by the Highways Authority, the new roads and any highway drainage will be required to comply with Nottinghamshire County Council's current highway design guidance and specification for roadworks. The Advanced Payments Code in the Highways Act 1980 applies and under section 219 of the Act payment will be required from the owner of the land fronting a private street on which a new building is to be erected. The developer should contact the Highway Authority with regard to compliance with the Code, or alternatively to the issue of a Section 38 Agreement and bond under the Highways Act 1980. A Section 38 Agreement can take some time to complete. Therefore, it is recommended that the developer contact the Highway Authority as early as possible.It is strongly recommended that the developer contact the Highway Authority at an early stage to clarify the codes etc. with which compliance will be required in the particular circumstance, and it is essential that design calculations and detailed construction drawings for the proposed works are submitted to and approved by the County Council (or District Council) in writing before any work commences on site.All correspondence with the Highway Authority should be addressed to:- NCC (Highways Development Control) (Floor 3)Nottinghamshire County Council County Hall Loughborough Road West Bridgford Nottingham, NG2 7QP
Planning Practice Guidance and section H of the Building Regulations 2010 detail surface water disposal hierarchy. The disposal of surface water by means of soakaways should be considered as the primary method. If this is not practical and there is no watercourse is available as an alternative other sustainable methods should also be explored. If these are found unsuitable, satisfactory evidence will need to be submitted, before a discharge to the public sewerage system is considered. Severn Trent Water advises that there is a public sewer located within the application site. Public sewers have statutory protection by virtue of the Water Industry Act 1991 as amended by the Water Act 2003 and you may not build close to, directly over or divert a public sewer without consent. You are advised to contact Severn Trent Water to discuss your proposals. Severn Trent Water will seek to assist you in obtaining a solution which protects both the public sewer and the proposed development. They may obtain copies of our current guidance notes and application forms for diversions from either our website (www.stwater.co.uk) or by contacting our Developer Services Team (Tel: 0800 707 6600).
No vegetation clearance or ground works shall take place on site during the bird nesting season (1st March to 31st August inclusive in any given year), unless pre-commencement checks for nesting birds have been undertaken by an appropriately qualified ecologist. If any nesting birds are found to be present, details of any proposed mitigation measures shall be submitted to and approved in writing by the Borough Council before the development commences. The mitigation measures shall be implemented in accordance with the approved details before development commences, unless otherwise prior agreed in writing by the Borough Council.
The applicant is advised that any site clearance works are undertaken outside of the bird breeding season - October to February inclusive.
The applicant is advised that conditions 16 and 17, relating to the requirement for a further badger survey and a survey regarding the potential presence of Great Crested Newts shall be read in conjunction with the submitted Ecological Appraisal Report by JJH Consulting Ltd December 2019.
Planning Statement - The Borough Council has worked positively and proactively with the applicant in accordance with paragraph 38 of the National Planning Policy Framework (2021). Negotiations have taken place during the assessment of the application to address adverse impacts identified by officers. Amendments have subsequently been made to the proposal, addressing the identified adverse impacts, thereby resulting in a more acceptable scheme and a favourable recommendation.
The developer is encouraged to consider upgrading the EV charging facilities to incorporate additional mode 3 charging capability as this will help future proof the development and improve its sustainability. A suitable 'IEC 62196' electrical socket (minimum rated output of 3.7kw /16A) can be provided in addition to the standard 3 pin socket to allow 'Mode 3' charging of an electric vehicle. Mode 3 charging, using a suitable cable and charging point, allows Smart charging of electric vehicles. All electrical circuits/installations shall comply with the electrical requirements of BS7671:2008 as well as conform to the IET code of practice on Electrical Vehicle Charging Equipment installation (2015).
In relation to the lighting condition above the submission of a bat-sensitive lighting scheme, should be developed in accordance with the Bat Conservation Trust publication "Artificial Lighting and Wildlife - Interim Guidance: recommendations to help minimise the impact of artificial lighting" dated June 2014.
The attached permission is for development which will involve building up to, or close to, the boundary of the site. Your attention is drawn to the fact that if you should need access to neighbouring land in another ownership in order to facilitate the construction of the building and its future maintenance you are advised to obtain permission from the owner of the land for such access before beginning your development.
The proposed development lies within a coal mining area which may contain unrecorded coal mining related hazards. If any coal mining feature is encountered during development, this should be reported immediately to The Coal Authority on 0845 762 6848. Further information is also available on The Coal Authority website at www.coal.decc.gov.uk.Property specific summary information on past, current and future coal mining activity can be obtained from The Coal Authority's Property Search Service on 0845 762 6848 or at www.groundstability.com.
You are advised that planning permission does not override any private legal matters which may affect the application site, over which the Borough Council has no jurisdiction (e.g. covenants imposed by former owners, rights of light, etc.).
The applicant is advised that all planning permissions granted on or after 16th October 2015 may be subject to the Community Infrastructure Levy (CIL). Full details of CIL are available on the Council's website. The proposed development has been assessed and it is the Council's view that CIL IS PAYABLE on the development hereby approved as is detailed below. Full details about the CIL Charge including, amount and process for payment will be set out in the Regulation 65 Liability Notice which will be sent to you as soon as possible after this decision notice has been issued. If the development hereby approved is for a self-build dwelling, residential extension or residential annex you may be able to apply for relief from CIL. Further details about CIL are available on the Council's website or from the Planning Portal: www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil