130 Application No. 2020/1255 - Land At Chase Farm (former Gedling Colliery), Adjacent to Arnold Lane and Land off Lambley Lane, Gedling pdf icon PDF 502 KB

Minutes:

Hybrid application seeking permission for a balancing Lagoon (Full Application) and Outline permission for the Local shops, access and associated parking.

 

The Head of Development and place introduced the report.  He informed Members of a typo in the header of the report as the applicant was Keepmoat Homes and the agent was Armstrong Burton Architects and not AC Holdings and Pegasus.

 

 

RESOLVED:

 

To Grant Full Planning Permission: Subject to the owner entering into a deed of variation amending the original Section 106 Agreement to planning approval: 2015/1376 with the Borough Council as Local Planning Authority and with the County Council as Local Highway and Education Authority for the provision of, or financial contributions towards affordable housing, open space, healthcare facilities, highways, educational, air quality, a local labour agreement and library facilities; and subject tothe conditions listed for the reasons set out in the report.

 

Conditions

 

1.         Development of the balancing lagoon shall commence no later than 3 years from the date of this permission and shall proceed in accordance with the details as approved under condition 2 and in accordance with details as may be approved under conditions 3, 5, 6, 7, 9 and 10.

 

2.         This permission shall be read in accordance with the application form and following list of approved drawings:

 

17057E - P100 rev - - Location plan

17057E - P101 rev A – Existing site masterplan

17057E - P103 rev B - Proposed site plan

17057E - P105 rev A - Site Sections

Deign and Access Statement (Updated received on 30 March)

 

The development shall thereafter be undertaken in accordance with these plans/details.

 

3.         Prior to above ground works commencing on the balancing lagoon, details of both hard and soft landscape works shall be submitted to and approved in writing by the Local Planning Authority.  The details as approved shall be completed no later than the first planting season once the earthworks for the lagoon have been substantially complete.  These details shall include a schedule (including planting plans and written specifications, including cultivation and other operations associated with plant and grass establishment) of  trees, shrubs and other plants, noting species, plant sizes, proposed numbers and densities. The scheme shall be designed so as to enhance the nature conservation value of the site, including the use of locally native plant species.  Details of any hard surfacing materials would also need to be identified.

 

4.         Application(s) for approval of all reserved matters for the local centre shall be made to the Local Planning Authority no later than 3 years from the date of this permission, and the development thereby authorised for the Local Centre shall be begun no later than 2 years from the date of this permission or 2 years from the date of the approval of the final reserved matter, whichever is the later.

 

5.         Prior to the commencement of development the following shall be submitted to and approved in writing by the Local Planning Authority:

 

Site Characterisation

 

An assessment of the nature and extent  ...  view the full minutes text for item 130