15 Carlton Square Regeneration Scheme PDF 217 KB
Report of the Service Manager Economic Growth and Regeneration.
Additional documents:
Minutes:
The Service Manager Economic Growth and Regeneration introduced a report, which had been circulated in advance of the meeting, updating on the progress of the Carlton Square Improvement scheme and seeking approval for further progression of the project.
RESOLVED to:
1) Thank officers for the recommendations and the work done so far in engaging with businesses;
2) Approve the final scheme of improvement works for Carlton Square car park as shown at Appendix 4 to the report;
3) Authorise the Chief Executive to submit an application for planning permission for the approved scheme at Carlton Square car park;
4) Delegate authority to the Service Manager of Economic Growth and Regeneration to make any minor amendments to the approved scheme as required during the planning application process;
5) Approve the decrease in the total project budget from £600,000 to £450,000 to reflect that the Council is only delivering part of the overall comprehensive scheme in its ownership;
6) Delegate authority to the Director of Organisational Development and Democratic Services to negotiate and enter into a legal agreement with BNP Paribas for the comprehensive development of Carlton Square, subject to the grant of planning permission and external funding being secured by the Council;
7) Approve an additional and separate capital budget of £25,000 for the improvement works to the proposed service yard to be funded by a contribution from the Economic Development Reserve; and
8) Note the progress to date, as set out in the report, and the intention to apply for funding for the works from the D2N2 LEP N2TC fund.