Issue - meetings

Planning Application 2018/0471

Meeting: 08/08/2018 - Planning Committee (Item 38)

38 Application Number 2018/0471 - Land at Ashwell Street, Netherfield pdf icon PDF 976 KB

Minutes:

Construction of a new medical centre and pharmacy including associated car and cycle parking facilities, sub-station and landscaping.

 

Caitriona Kennedy, the applicant, spoke in support of the application.

 

RESOLVED:

 

To grant planning permission subject the following conditions:

 

Conditions

 

 1         The development must be begun not later than three years beginning with the date of this permission.

 

 2         This permission shall be read in accordance with the following plans submitted to the Local Planning Authority; drawing numbers 1442-99, 1442-200 Revision J, 1442-205 Revision A and 1442-300 Revision A received on 8th May 2018 and drawing 1442-100 Revision H received on 23rd July 2018 and the emails from the Agent received on 25th and 27th July 2018 confirming the appearance of the bin store and VRF enclosure screens and the height of the VRF enclosure screen.

 

 3         In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported in writing immediately to the Local Planning Authority and development must be halted immediately on that part of the site until such time that the Borough Council has given written approval for works to recommence on site. Once contamination has been reported to the Local Planning Authority, an assessment of contamination must be undertaken.  This assessment shall include a survey of the extent, scale and nature of contamination and an assessment of the potential risks to human health, property, adjoining land, controlled waters, ecological systems, archaeological sites and ancient monuments.  The assessment shall be undertaken by a competent person and shall assess any contamination of the site whether or not it originates on site.  Where remediation is necessary, a written remediation scheme, together with a timetable for its implementation and verification reporting, must be submitted to and approved in writing by the Local Planning Authority.  The remediation scheme and verification reporting shall be implemented as approved.

 

 4         Before development is commenced there shall be submitted to and approved in writing by the Local Planning Authority details of a Dust Management Plan.  The plan shall be produced in accordance with 'The Control of Dust and Emissions from Construction and Demolition' (Best Practice Guidance).  The plan shall be implemented in accordance with the approved details and shall be retained for the duration of the construction period.

 

 5         Prior to the erection of any external lighting there shall be submitted to and approved in writing by the Local Planning Authority details of all such lighting, including levels of illumination and a lux plot of the estimated luminance, to be provided on the proposed building or elsewhere within the site.  Any security lighting/floodlighting to be installed, shall be designed, located and installed so as not to cause a nuisance to users of the highway or adjacent properties. The external lighting shall be provided in accordance with the approved details and shall be retained for the lifetime of the development.

 

 6         Prior to the first occupation of the building hereby approved there shall be  ...  view the full minutes text for item 38