Reference: D861
Decision Maker: Deputy Chief Executive and Director of Finance
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
To obtain a feasibility study to inform
proposed constructions costs and programme of works to enable the
extension of the Garden or remembrance at Carlton
cemetery
to utilise the SCAPE regional construction
framework to obtain feasibly studies for the proposed works at
Carlton cemetery to extend the garden of remembrance. The
feasibility work will progress the project by identifying
construction costs and developing a programme of works and risk
register. The framework partner will be Lindums.
Under the SCAPE framework the feasibility work
is undertaken by the framework partner at their costs (except
surveys). The framework allows the Council to work with the
delivery partner at an early stage to develop a programme of works
within budget to meet the Council’s objective. The
feasibility work is completed within a short timescale of between
6-8 weeks and the Council will receive a full feasibility report at
the end of the process.
Not to access the framework and either pay a
third party to undertake the feasibility studies on behalf of the
Council or go to the open market to tender for the works without
any detailed estimate as to costs or feasibility work being
undertaken.
Publication date: 18/04/2019
Date of decision: 11/04/2019