Decision details

To grant approval for an extension of the license to allow works connected with the Gedling Access Road to take place within the Gedling Country Park.

Reference: D796

Decision Maker: Deputy Chief Executive and Director of Finance

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To allow site clearance and drainage works to take place within the Gedling Country Park in connection with the Gedling Access Road.

Decision:

To approve the extension of the licence to allow the clearance and drainage works to take place within the Gedling Country Park.

Reasons for the decision:

The works will allow progress on the Gedling Access Road.

Alternative options considered:

An alternative would be not to allow the works to take place however this would hold up progress of the Gedling Access Road.

Publication date: 18/01/2019

Date of decision: 21/03/2018