Reference: D768
Decision Maker: Portfolio Holder for Sustainable Growth and Economy
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
To seek the Portfolio Holder’s approval
to:
a) Allocate and establish a budget of £3,500 towards the
Cinderpath capital project for the lighting element of the
scheme;
THAT:
the Portfolio Holder for Growth and Regeneration approves
a)A virement to establish an additional budget of £3,500 on
the Cinderpath capital project for the lighting element of the
scheme to be funded from the CIL Non-Parish Neighbourhood Funding
contributions.
a)To ensure that the neighbourhood portion of
CIL collected receipts are expended in accordance with the CIL
Regulations 2010 (as amended) and statutory guidance.
Two alternative options are potentially
available to pursue.
Firstly there is the opportunity to allocate CIL monies to
alternative schemes contained on the Local Infrastructure Schedule
and Allocations consultation. However, although some comments
received may suggest alternative projects could be funded, the
other schemes have been assessed as not being suitable for funding
at this time, either on the ground of project suitability (not
meeting CIL Regulation 59F), alternative funding streams available
or due to the unavailability of full funding (either from CIL or
external streams).
The second alternative option would be to the remove project from
the potential shortlist to allow for the CIL Non-Parish
Neighbourhood Funding pot to accumulate further or await the
further identification of alternative schemes. The implications of
this could see a suitable project not funded and may prevent
projects that are due to be matched funded not being delivered
fully.
Publication date: 07/11/2018
Date of decision: 07/11/2018
Accompanying Documents: